Montana Department of Transportation

Active Project

Rouse-Oak / Story Mill

For the week of October 16:

Excavation and storm drain installation have both been completed in the second section of the project, which extends from Bond Street to just south of Birdie Drive. Road grading, gravel and concrete placement are currently underway with paving taking place this coming week, weather permitting. Knife River crews also continue with the installation of curb and sidewalk in this zone.

Deck repair work on the bridge spanning the East Gallatin River continues to take place. Work on the bridge will include rail, curb and sidewalk.

Drivers are advised to please plan additional travel time, watch for flaggers, expect travel delays, and to remember that fines double in work zones. Using alternate routes, if possible, is recommended.

Continued closures on N. Rouse (E. Griffin & E. Bryant)

As crews finish up installing curb and gutter near East Griffin Drive and East Bryant Drive, businesses and residents on these streets can anticipate moderate detours. East Griffin Drive and East Bryant Drive are currently closed at North Rouse Ave. Access for all businesses and residents on these streets will be available through alternate routes. Those wishing to access East Griffin Drive are advised to use Story Mill Road; East Bryant Drive can be reached through Bond Street. These closures are anticipated to remain in place for several weeks while improvements are made.

Want more info on the project?

Hear us:

  • XL Country 100.7 FM
  • The Moose 95.1 FM
  • K-Sky Country 106.9 FM
  • KBOZ 99.9 FM
  • KOBZ 97.5 FM
  • 96.7 KISS FM
  • My 103.5 FM

Ask us:

Questions or concerns may be addressed to Steve Baeth at 406-388-6832. To sign up for weekly email updates on the Rouse-Oak / Story Mill project, please submit a request .

Join us:

There will be scheduling meetings for the Rouse-Oak Project taking place once a month at 1804 North Rouse.

The meetings will be open to the public and offer a chance to discuss progress and get answers to questions about the project from members from Knife River and MDT.

The next meeting will take place on Tuesday, October 24 at 11am.

Work Schedule

Crews will work Monday through Friday from approximately 7 a.m. to 6 p.m. For the duration of the Rouse-Oak to Story Mill Road Project, traffic may occasionally be reduced to one lane, which may create short delays, increased traffic, temporary loss of access and detours for adjacent residents and businesses. Drivers are advised to please plan additional travel time, please watch for flaggers and remember that fines do double in work zones.

Project Overview

Headed by general contractor, Knife River, work on the Rouse-Oak / Story Mill Bozeman project restarted on Tuesday, April 11.

Construction of this project began on November 16, with minor exploratory excavation and utility location and continued through mid December. The project then shut down for the winter and was scheduled to resume beginning to mid April.

The project will extend on Rouse Avenue from Oak Street north to Story Mill Road and includes multiple improvements, such as widening the road as well as adding a turning lane from Bond Street to Story Mill Road. There will also be the addition of new bike paths, sidewalks and landscaping. Additionally, Knife River will install a new storm drain system, water system, and sanitary sewer system as part of the project.

The overall goal of the Rouse-Oak / Story Mill Bozeman project is to develop a roadway better suited to meet the needs of the Bozeman community. The anticipated completion date for the Rouse-Oak / Story Mill Bozeman project is October 2017, weather permitting.

For the duration the Rouse-Oak / Story Mill Bozeman project, Knife River recommends using alternate routes and encourages drivers to plan additional travel time, especially from 7:00 am to 6pm, as there will be traffic delays during these times.