The Peoples Way is a 56.3 mile corridor on US 93 from Evaro to Polson that traverses the Flathead Indian Reservation.
The safety and road capacity improvements underway are a collective vision of MDT, the Confederated Salish & Kootenai Tribes of the Flathead Nation and the Federal Highway Administration. The Peoples Way sets a new standard for road design, commitment to the environment, and intergovernmental collaboration.
Sign up for project updates
View aerial images
Current Construction Information
Mud Creek Structures
- Project limits North and South bound, mile Post 50 to 51
- This two-phase project includes construction of two bridges at Mud Creek
- The first phase of this project that began in April of 2006 the second phase will be completed in 2007
- The bridges being constructed will also act as wildlife crossings
- Old Hwy 93 west of the intersection with US 93 is closed indefinitely
- Activities will be taking place off the roadway, reduced speeds 35 mph
- Be prepared for a reduced speed limit of 35 mph
- This project is complete.
- Updated August 19, 2008
Spring Creek to Minesinger Trail
- Project limits are from mile post 48.30 to 56.00
- Project to begin September 4, 2007
- This project will consist of re-construction resulting in a divided 4 lane through Pablo
- Expect 35 mph speed limits, brief road closures, short delays, detours, portable stop lights.
- Motorists should watch for trucks and equipment entering the roadway
- Starting November 9, 2007 there will be intermittent daily road closures for Division Street, West Pablo Road and Minesinger Trail.
- South of Mud Creek, Old HWY-93 is closed on the east and west side of US-93. There will be an alternative access via Light Road.
- Starting March 18, 2008 Major Houle road will been closed for an extended period of time. Motorists will be advised of changes via portable message signs.
- Beginning Monday April 7, 2008, Old Hwy-93 will be closed at the intersection with US 93 at mile marker 53.3 until further notice.
- West Pablo Road will be closed starting April 8, 2008 for approximately 2 weeks. There will be alternate access to businesses via New Division Street and Light Road via Old Hwy 93.
- Division street and approches on the west side of US 93 will be closed intermittently over the next 2 weeks for paving.
- Chip Seal is wrapping up and striping is underway.Old 93 is now open on the east side south of Pablo.There will be short delays and reduced speeds
- Updated August 19, 2008
Evaro to McClure Road
- Project limits begin at mile post 6.4 and extend North through Evaro, into the Flathead Nation and end at mile Post 12.8.
- This project will consist of re-construction resulting in the extension of about 1.4 miles of the four-lane undivided roadway, two-lane roadway with turn and alternating passing lanes for north and southbound traffic, relocation of approximately one mile of MRL Railroad line in Evaro, ten wildlife crossing structures including a new bridge over the MRL Railroad near Joe's Smoke Ring and one wildlife over-crossing.
Statewide Road Construction Report