The Valley Spur Intersection Improvement project began in January of 2017 and design will be complete in February of 2019.

Task Timeframe
Project Scoping January 2017
Report and Survey Development January 2017 – August 2018
Plan-In-Hand May 2018
Final Plan Review September 2018
Transmit to Contract Plans January 2019
Public Involvement July 2017 - August 2018
Project Team Meetings January 2017 – February 2019