Active Project - East of East Helena – East

East of East Helena – East

Project Schedule

Phase Date Status
Traffic Study June 2015 – December 2016 Complete
Plans Development May 2017 – April 2019 Underway
Alignment and Grade April 2018 Complete
Environmental Document April 2019
Plan-in-Hand May 2019
Final Plan Review January 2020
Environmental Permitting May 2019 - February 2020
Right-of-Way Negotiations October 2019 – April 2020
Utility Relocation Spring - Summer 2020
Project Letting January 2021
Construction Summer 2021