Missoula Concrete Rehab

Missoula Concrete Rehab logo

Weekly Updates

September 20-25, 2020

  • Nightwork resumes on the Missoula Concrete rehab project for the week of September 20. Crews will be working through project limits from 7 PM – 7 AM., including Friday night into early Saturday morning.
  • Within the concrete grinding closure, crews will also be installing underground electrical wires through electrical boring methods.
  • Crews will work on the sidewalks and add ADA upgrades from I-90 to Expressway to ensure access for all. The Grant Creek/I 90 west-bound on ramp lanes will also be under construction as crews reconstruct the area as well. At the intersections within this project area, crews will work on the asphalt approach tie-ins as well as the shared-use paths.
  • Drivers should plan for closures of multiple lanes. Throughout the project, both north and southbound lanes will be reduced.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

Previous Updates

September 13-19, 2020

  • Missoula Concrete Rehab construction will again see nightwork from 7 PM to 7 AM. Crews will resume work on Sunday night and will continue work through Friday and into Saturday morning. Construction will be focused near River Road, in both directions for additional concrete grinding and joint resealing. Within the concrete grinding closure, crews will also be installing underground electrical wires through electrical boring methods.
  • Crews will work on the sidewalks and add ADA upgrades from I-90 to Expressway to ensure access for all. The Grant Creek/I 90 west-bound on ramp lanes will also be under construction as crews reconstruct the area as well. At the intersections within this project area, crews will work on the asphalt approach tie-ins as well as the shared-use paths.
  • Drivers should plan for closures of multiple lanes. Throughout the project, both north and southbound lanes will be reduced.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

September 7-10, 2020

  • Missoula Concrete Rehab construction will again see nightwork from 7 PM to 7 AM. Crews will resume work on Tuesday night. Construction will be focused near River Road, in both directions for additional concrete grinding.
  • The roadway concrete sections will be resealed at the intersections of Brooks and I 90. The north and southbound Grant Creek/I 90 ramps will also be under construction as crews reconstruct the area.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

August 30 – September 3, 2020

  • Missoula Concrete Rehab construction will again see nightwork from 7 PM to 7 AM. Construction will be focused near River Road, in both directions. Closures will be on Reserve, from Brooks to River Road on the inside lanes and median for concrete grinding. Additionally, the outside lane of Reserve Street, from River Road to I 90 will be closed while crews reseal sections of the roadway.
  • The Mullan/Reserve intersection will also have partial closures for electrical work, where closures will be taking place between Mullan Road and I 90.
  • Lastly, the sidewalks at Reserve and Expressway will see additional ADA upgrades and the median at Reserve and Grant Creek will again be closed. Grant Creek medians and turn lanes are being constructed.
  • Both north and southbound lanes will be reduced, and no work will take place for the Labor Day holiday.
  • Crews have moved staging. Grant Creek residents should hear far less construction noise for the remainder of the project.
  • Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • At the Grant Creek/I-90 intersection, crews will be fully reconstructing the road to include a southbound travel lane and bike lane on Grant Creek Road. A southbound right-turn lane will also be added to Grant Creek Road for access to the I-90 westbound entrance ramp. A new traffic signal will be installed as well.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Weekly project updates will continue to be provided every Friday throughout construction. If you have any questions, please call 406-207-4484 or email . We are here to help address your concerns during this project.

August 23-28, 2020

  • It’s another busy week for the Missoula Concrete Rehab construction project, with nightwork from 7 PM to 7 AM. Construction will be intermittent from Brooks to I-90 to reseal roadway sections.
  • The Mullan/Reserve intersection will also have partial closures for electrical work.
  • Lastly, the sidewalks at Reserve and Expressway will see additional ADA upgrades and the median at Reserve and Grant Creek will again be closed.
  • Both north and southbound lanes will be reduced during construction. Traffic signals will be in place.
  • Crews have moved staging. Grant Creek residents should hear far less construction noise for the remainder of the project.
  • Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • At the Grant Creek/I-90 intersection, crews will be fully reconstructing the road to include a southbound travel lane and bike lane on Grant Creek Road. A southbound right-turn lane will also be added to Grant Creek Road for access to the I-90 westbound entrance ramp. A new traffic signal will be installed as well.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Weekly project updates will continue to be provided every Friday throughout construction. If you have any questions, please call 406-207-4484 or email . We are here to help address your concerns during this project.

August 16-21, 2020

  • Missoula Concrete Rehab construction will continue with nightwork this week, from 7 PM to 7 AM. Construction will be spread across Reserve Street, from Brooks to I 90.
  • The intersection of Reserve and Brooks will be a focus and drivers should plan for additional time when traveling in the area. The outside lanes of Brooks, River Road, Mullan, and Raser Drive will all see concrete work.
  • Both north and southbound lanes will be reduced during night construction for additional concrete work. Traffic signals will be in place.
  • Sidewalk work and ADA upgrades at the Reserve, Expressway, and Howard Raser Drive intersections will be done throughout the week.
  • Crews have moved staging. Grant Creek residents should hear far less construction noise for the remainder of the project.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

August 9-15, 2020

  • I-90/Grant Street/Reserve Website Update: August 9-15, 2020
    with crews working from 7 PM to 7 AM. Construction will be spread across Reserve Street, from Books to I 90.
  • Throughout the project, concrete crews will be repairing previously cracked panels. This involves tying bars through drilled holes to keep the pieces in place. Somewhat like cross-stitching when sewing.
  • Both north and southbound lanes will be reduced during night construction for additional concrete work. Traffic signals will be in place.
  • Sidewalk work and ADA upgrades at the Reserve, Expressway, and Howard Raser Drive intersections will be done throughout the week.
  • Crews have moved staging. Grant Creek residents should hear far less construction noise for the remainder of the project.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

August 2-7, 2020

  • Missoula Concrete Rehab construction will continue this week, with crews working from 7 PM to 7 AM. Construction will be spread across Reserve Street, from Books to I 90.
  • Both north and southbound lanes will be reduced during night construction for additional concrete work. Traffic signals will be in place.
  • Sidewalk work and ADA upgrades at the Reserve, Expressway, and Howard Raser Drive intersections will be done throughout the week.
  • Crews have moved staging. Grant Creek residents should hear far less construction noise for the remainder of the project.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

July 26-30, 2020

  • Construction on the Missoula Concrete Rehab project will continue the week of July 26 where crews will work at night - from 7 PM to 7 AM. Construction will be focused on the northern end of the project, near the Reserve Street intersections with Expressway and Howard Raser Avenue, where crews will be making ADA and sidewalk improvements. Electrical work will continue between Mullan Road and Interstate 90.
  • The middle lanes of Reserve Street; both north and southbound from Mullan Road to I-90 will have concrete replacement this week.
  • Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

July 19-25, 2020

  • Construction on the Missoula Concrete Rehab project will continue the week of July 19 where crews will work at night - from 7 PM to 7 AM. Construction will be focused on the northern end of the project, near the Grant Creek intersection. ADA ramp work will be starting and electrical work will continue.
  • The middle lanes of Reserve Street; both north and southbound from Mullan Road to I-90 will have concrete replacement this week.
  • Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call 406-207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

July 13-17, 2020

  • Construction on the Missoula Concrete Rehab project will continue the week of July 13. This is a busy week. Construction will be both northbound and southbound of Reserve Street on the middle and outside lanes. Activities will be focused from Brooks Street and River Road; and Mullan Road to I-90.
  • Intersections along these routes will also see some electrical work, specifically at Third Street, Mount, and Brooks.
  • Regular construction hours will be at night, Monday through Friday, 7 p.m. to 7 a.m. Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • At the Grant Creek/I-90 intersection, crews will be fully reconstructing the road to include a southbound travel lane and bike lane on Grant Creek Road. A southbound right-turn lane will also be added to Grant Creek Road for access to the I-90 westbound entrance ramp. A new traffic signal will be installed as well.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Weekly project updates will continue to be provided every Friday throughout construction. If you have any questions, please call 406-207-4484 or email .

June 29 - July 3, 2020

  • The Reserve/I-90/Grant Creek project is underway!
  • This week, crews will be working between Mullan Road and I-90, both in the northbound and southbound lanes. To reduce holiday traffic, construction will pause starting Friday, July 3 at 7 a.m. and resuming Monday evening.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • At the Grant Creek/I-90 intersection, crews will be fully reconstructing the road to include a southbound travel lane and bike lane on Grant Creek Road. A southbound right-turn lane will also be added to Grant Creek Road for access to the I-90 westbound entrance ramp. A new traffic signal will be installed as well.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call (406) 207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.

June 15 - 19, 2020

  • The Reserve/I-90/Grant Creek project is starting construction the week of June 22. Construction hours will be at night, Monday through Friday, 7 p.m. to 7 a.m. Travel on Reserve Street, between Brooks Street and Interstate 90, will be limited to one-lane with a traffic signal in place during night hours. At the Grant Creek Road and Interstate 90 intersection, travel will be limited to one-lane at night with flaggers in place.
  • On Reserve Street, crews are resurfacing the road, restoring 5.4 miles of roadway from Brooks Street to I-90. This will extend the life of the road and keep it smooth for years to come.
  • At the Grant Creek/I-90 intersection, crews will be fully reconstructing the road to include a southbound travel lane and bike lane on Grant Creek Road. A southbound right-turn lane will also be added to Grant Creek Road for access to the I-90 westbound entrance ramp. A new traffic signal will be installed as well.
  • Crews will also add ADA upgrades to the I-90 eastbound ramps, the I-90 and Reserve Street intersection, and the Expressway and Reserve Street intersection to ensure access for all.
  • This project is anticipated to finish by the end of 2020. By working at night, MDT aims to ease construction-related traffic congestion. However, we understand that some businesses may experience construction noise during the later hours. MDT is committed to minimizing noise impacts and travel delays by working efficiently to finish the road work as quickly as possible. Please always feel free to reach out with any concerns.
  • Our project hotline is open for questions between 9 a.m. and 5 p.m., Monday through Friday. Call (406) 207-4484 to reach us. Text updates are also available. To register text GOODROADSMSLA to 41411.