Bench Boulevard Reconstruction Bench Boulevard Reconstruction links

· Study Focus
· Schedule
· Comments
· Public Input/Documents

Bench Boulevard Reconstruction contacts
Stefan Streeter
MDT Billings Administrator
424 Morey Street
PO Box 20437
Billings, MT 59104-0437
| 406/657.0268

Miki Lloyd
MDT Consultant Prj Eng
2701 Prospect Ave
PO Box 201001
Helena, MT 59620-1001
| 406/444.9200

Kirk Spalding
Sanderson/Stewart Prj Mgr
1300 N Transtech Way
Billings, MT 59102
| 406/656.5255

Project Schedule

photo of Bench Blvd

Status

  • Phase I is at approximately the 90% design stage
  • Phase II is at approximately the 30% design phase
  • Informational meeting was held on August 3, 2009 in the Yellowstone Room at the Metrapark for landowners along the Phase I project.
  • Informational meeting was held on September 15, 2009 in the gymnasium of Bitterroot Elementary for landowners along both Phase I and Phase II projects.
  • Informational meeting was held on June 23, 2011 at Bitterroot Elementary for landowners along both phase I and Phase II projects.

Construction

  • Phase I construction is tentatively scheduled for 2012-2013
  • Phase II construction is anticipated in 2016. MDT desires to accelerate this schedule and efforts will be made to achieve this, however it is dependent on the availability of funding.