Public Involvement - Active Projects

Project Schedule

Approximate Construction Schedule (weather dependent):

Beginning May 8
Beartooth Lane
Goran will mobilize and begin work on Beartooth Lane. There will be no impacts to Broadway from 2nd to Robinson.

Mid-May – Early June
2nd Street to Robinson
Goran will close Broadway between 2nd and Robinson. This closure is anticipated to be completed by the first week of June.

Early June – Mid- July
5th Street and 2nd Street
OPEN JULY 2 – 5
Goran will close Broadway between 5th Street and 2nd Street. The section will be open to traffic during the Fourth of July activities, and completed in mid-July.

Mid-July – Mid-August
8th Street – 5th Street
Goran will close Broadway between 8th Street and 5th Street. The section is anticipated to be complete by mid-August.

Mid –June – October
Red Lodge South Mill and Overlay
This section will remain open during construction.

August – October
Brewery Hill
This section will remain open during construction

Access to all businesses will be maintained during construction. For more information please download the traffic impact card.