Active Project

Russell Street


Preliminary Design

  • Final Construction Plans are being developed for the Russell Street segment from Dakota St to West Broadway.
  • An open house was held on May 27, 2015 for the West Broadway to Dakota project segment.
  • May 2015 - 90% Plans are complete for the West Broadway to Dakota.
  • Surveying and soil sampling for the project are complete.
  • Fall 2013 - Preliminary Design (30%) are complete for Mount to Dakota and Dakota to West Broadway.
  • An open house and City meeting were held in the Fall of 2013. Additional open houses will be scheduled in the future.


  • Construction is anticipated for Dakota to West Broadway in 2017.