
Traffic Control Update
During construction motorists traveling through the project area can expect a 16-foot width restriction, reduced speeds, single lane traffic, and possible delays.
All wide loads should coordinate alternate routes with Motor Carrier Services at 406-444-7262.
June 25, 2025
Asphalt paving began this week and is expected to continue through next week. After paving is finished, roadway signs will be installed, and striping will be applied.
Please use caution while traveling through the project area.
June 10, 2025
The following work has been completed at both project sites:
- Gravel has been placed along the roadway shoulders
- Topsoil has been added
- Seeding has been done on the roadway shoulders
- Fencing installation
Next week, asphalt paving is scheduled to begin. After paving is finished, roadway signs will be installed, and striping will be applied.
Please use caution while traveling through the project area.
April 1, 2025
The Montana Department of Transportation (MDT) and its partner KH Civil Contractors Inc. are expecting to begin construction this spring.
If you have questions or comments, please do not hesitate to contact the project communications team at mt200@dowl.com or calling the project hotline at 833-377-0453.