Contractor's System Project Question and Answer Forum

BULLETIN BOARD                                                                                                                                                                                                                                                           
            To request an alternative accessible format of these documents, please contact MDT’s ADA Coordinator at 406-444-5416, Montana Relay Service at 711, or by email at mdtaccessibilityrequest@mt.gov.                    
__________________________________________________________________________________________________________________________________________________________________________________
___________________________________________________________________________________________________________________________________________________________________________________
Billings Bypass – Johnson Lane Interchange Extended Advertisement (UPDATED 6/1/26)
The BBP – Johnson Lane Interchange is an MDT project in Yellowstone County to reconstruct the Johnson Lane Interchange on Interstate 90. Advertisement for the project is scheduled to begin on July 16th, 2026 running through August 27th, 2026. The Q&A Forum will be open for questions beginning on Thursday, July 16th and will close on Friday, August 21st at 8 am. The Preliminary Bid Package is available on the MDT Contracting & Bidding webpage at the following address Preliminary-Copy-Proposal-and-Plans

The Q&A Forum period for all other projects in the August 27, 2026 letting will remain unchanged, with the Q&A Forum opening to questions beginning on July 30th and closing to questions on Monday, August 24th at 8 am.

_____________________________________________________________________________________________________________________________________________________________________________________________________________________________
Ekalaka Exigency Project
MT-323 Culvert – S of Ekalaka is an exigency project to replace the failing 108-inch CSP culvert on MT 323 at R.P. 22.9.  Due to the risk of failure of the pipe there is a severe threat to the integrity of the roadway and the safety of the travelling public.  The project will be included in the scheduled August 6th, 2026 bid letting with advertising beginning on July 9th and award on August 18th.  The Notice to Proceed will be expedited and is expected to be on or around August 31st, 2026.

_____________________________________________________________________________________________________________________________________________________________________________________________________________________________
Watch - Public Bid Opening - Live Stream: ZOOM MEETING INFORMATION 

______________________________________________________________________________________________________________________________________________________________________________________________________________________________

Advertised Projects: If you would like to receive the Invitation for Bids PDF document when projects are advertised, please send an email request to mdtcps@mt.gov. Follow the link for more information: EMAIL DISTRIBUTION
______________________________________________________________________________________________________________________________________________________________________________________________________________________________

201 - FORT PECK-NORTHWEST - June 25, 2026

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Tuesday 23-JUN-2026 01:41 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:00 PM
New Federal Wage Rates, General Decision Number MT20260080, are now in effect and hereby replaces General Decision Number MT20260079 found in the advertised proposal: WAGE RATES


Questions

-1-
Submitted: Friday 29-MAY-2026 11:51 AM
Company: Riverside Contracting Inc.
Contact: Estimating
Can MDT post the design files, mass diagram, dirt runs, and any additional geotechnical information.
Answer
Submitted: Monday 01-JUN-2026 02:50 PM
The design files for the requested project are posted here:  DESIGN FILES
The requested files do not represent the staked project, but are only design files.  The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.
In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.


Linked are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at the following link: GEOTECH REPORT

-2-
Submitted: Wednesday 03-JUN-2026 12:38 PM
Company: Riverside Contracting Inc.
Contact: Dennis Devous
Please confirm the Crushed Aggregate bid item. The Additional Surfacing Summary shows 13333 Cy of a leveling Cs. and this isn't added into the Total Bid Crushed Aggregate bid item. Please clarify what you want.
Answer
Submitted: Wednesday 17-JUN-2026 07:30AM

Please see note below Additional Surfacing summary frame “# FOR INFORMATION ONLY – USE EXCESS PULVERIZED MATERIAL FOR LEVELING”. Under Pulverized Material on the Notes page also states “USE THE EXCESS PULVERIZED MATERIAL FOR SHOULDER GRAVEL AND LEVELING (QUANTITES CALCULATED USING 8% SWELL)”.
 
It is expected that the project will produce approximately 23000 yd3 of excess pulverized material of which 13,333 yd3 will need to be incorporated along the corridor for leveling purposes to meet the vertical profile.

No additional payment will be made for the use of excess pulverized material to the final position to achieve grade.  Include the cost of incorporating of this material in the Pavement Pulverization bid item.  If additional crushed aggregate is required to make grade after the addition of excess pulverized material is complete, the additional crushed aggregate will be paid in accordance with standard specification 302.03.3 paid by the yd3.

-3-
Submitted: Friday 05-JUN-2026 09:14 AM
Company: Riverside Contracting Inc.
Contact: Estimating
In response to Question 1. The design files appear to be incomplete, lacking a subgrade surface and complete project alignment. There appears to be an inconsistency between the main grading frame and quantities calculated from the cross sections. Can MDT provide a dirt run for the project please?
Answer
Submitted: Wednesday 17-JUN-2026 07:33AM
-Due to the segmented nature of the project, there are multiple project alignment files that were provided.  A combined file for the entire length of the project has not been made.  A dirt run has not been generated for this project.

-4-
Submitted: Sunday 07-JUN-2026 11:30 AM
Company: Prince, Inc.
Contact: Mike Sharp
The NTP date in the proposal is August 24, 2026. Could this project be flexed to April 15th, 2027? The pit permitting process, mix design development and approval, and the fact that the emulsion injection process has limitations (weather, curing, etc..) lends itself to a 2027 start date. And the flexibility of a Flex Date NTP will still allow the successful bidder to work this fall if desired. Thank you.
Answer
Submitted: Tuesday 09-JUN-2026 09:36AM
Contract time will be revised to a flex time proceed date, effective April 19, 2027. Special provision #2, Contract Time is rescinded and replaced with the linked special provision, Contract Time – Flex Time Proceed Date: CONTRACT TIME

-5-
Submitted: Saturday 06-JUN-2026 06:08 PM
Company: Prince, Inc.
Contact: Mike Sharp
1.) There are nearly 100 approaches on the project and no quantities for the obliteration of the existing surfacing on the approaches. How will this obliteration be paid for?
2.) There are also several mailbox widenings that require pulverization that do not appear to have quantities set up in the pulverization summary. Will this be paid under the pulverization item?
3.) It appears that the pulverized pavement quantity is also included in the unclassified excavation quantity. Please provide a detailed breakdown of both quantities to help clarify which is to be paid as unclassified excavation and what is to be paid as pulverization.
4.) The note below the Additional Surfacing summary indicates that there will be 13,333 CY of leveling course material available for leveling. The last two pulverization projects have had either shrink (-4% on Reserve - E.) or zero swell (W. of Jordan - W.). What pay item will be used to address the shortfall if that occurs?
5.) Special Provision 20 reads that Corrective Aggregate (CAC) required for corrective work (leveling and digouts) prior to emulsion injection will be paid by the ton. That pay item and quantity is missing from the proposal. Please add that bid item and quantity to the documents and bid file.
Answer
Submitted: Wednesday 17-JUN-2026 08:00AM
1 - Approaches where CAC and PMS are listed, they are planned to be rebuilt and the quantities are included in Unclassified Exc, CAC and PMS bid items.  If there is only PMS quantiles listed, an overlay is planned. 
2 - The mailbox widening areas that need pulverized will be paid under the respective bid items.
3 - The pavement pulverization is not included in the Unclassified Excavation quantities.  The quantity for Excavation Unclassified (203 020 100) has been reduced to 108,853. The Pavement Pulverization (302 000 000) quantity has been increased to 215,806. Sheets 14 -16 have been updated. Sheet 16A is also hereby added to the plan set. An amendment will be issued; updated bid files will be posted. UPDATED SHEETS 14-16 AND 16A
4-See Q&A #2
5-See Q&A #2


UPDATED: Monday 22-JUN-2026 10:35 AM
Sheets 14 and 15 have been updated (see question #8): SHEETS 14-16 AND 16A

-6-
Submitted: Thursday 11-JUN-2026 12:28 PM
Company: Century Companies, Inc.
Contact: Estimating Estimating
We reached out to the contact listed in SP 17, and were instructed to ask any questions here. Can the department explain what the area actually is?
Answer
Submitted: Friday 12-JUN-2026 11:15AM
The location is a cultural resource that may be eligible for the National Register of Historic Places. It is a sensitive area that must not be disturbed. In consultation with the State Historic Preservation Office and the Fort Peck Tribal Historic Preservation Office, this location was identified for protection. The National Historic Preservation Act requires this location is protected. 

-7-
Submitted: Thursday 11-JUN-2026 02:26 PM
Company: Rinker Materials - Rapid City, SD
Contact: Brian Jenner
What are the cutoff wall depths for the following locations:
534+36 65x40 RCPA FETS Cutoff Walls Left and Right
687+02 102x62 RCPA FETS Cutoff Walls Left and Right
738+93 65x40 RCPA FETS Cutoff Walls Left and Right

The quantity shown in the plans for CONCRETE CLASS GENERAL for the locations does not match what is shown on MDT Drawing 552-04 to correlate the depth required.
The CONCRETE CLASS GENERAL quantity for the 65x40 cutoff wall is called out in the plans as 2.8 cu. yds. or 1.4 cu. yds. per cutoff wall. The value of 1.4 cu. yds. is shown in MDT Drawing 552-04 for RCPA (SQ. END) for 3 ft. depth, but these are FETS ends.
The CONCRETE CLASS GENERAL quantity for the 102x62 RCPA is called out in the plans as 3.8 cu. yds. or 1.9 cu. yds. per cutoff wall.
The value of 1.9 cu. yds. is shown in MDT Drawing 552-04 for RCPA (SQ. END), for 3 ft. depth, but the plans call out FETS ends.
Answer
Submitted: Tuesday 16-JUN-2026 02:15 PM
1: Both of these sites have foundation materials and should have H = 4’ per DD 552-00. For this size RCPA with FETS, quantity is 2.1 cu yd per pipe end.
2: This pipe should be H = 4’ since it has foundation material per DD 552-00. Cutoff walls are 2.6 cu yd each for this size RCPA with FETS.

The quantity for Concrete Class General (551020030) has been increased to 18.8 CUYD. Sheets 17, 18, 19 and 21 have been updated. SHEETS 17-19 AND 21

An amendment will be issued; updated bid files will be posted.


UPDATED: Monday 22-JUN-2026 10:40 AM
Sheet 21 has been updated (see question #8): SHEETS 17-19 AND 21

-8-
Submitted: Thursday 18-JUN-2026 10:46 AM
Company: Wickens Construction, Inc.
Contact: estimating
Can MDT verify the following lengths of culvert: 1) Drainage Pipe 24 in, 2) RCPA 30 in, 3) RCP 36 in, 4) RCP 42 in? There are over 4 miles of reconstruct areas on the project but no traffic gravel item. Would MDT consider adding a traffic gravel item to the project?
Answer
Submitted: Monday 22-JUN-2026 09:17 AM
MDT verified pipe lengths and found that for the 24" CSP, 30" RCPA and 42" RCP the summary tables are tabulated correctly and match the bid quantities. The 36" RCP was included in error and will be removed. MDT will also add 1000 yd3 of traffic gravel. Sheets 14, 15 and 21 have been updated: UPDATED SHEETS

Item added: Traffic Gravel – 301020268 – 1000.00 CUYD
Remove item: RCP 36 IN – 603012660 – 90.00 LNFT

An amendment will be issued; updated bid files will be posted.

-9-
Submitted: Friday 19-JUN-2026 01:32 PM
Company: Baranko Brothers Inc.
Contact: Jadyn Roller
On this project there are multiple right of way breaks in the fence and the standard drawings DWG 607-05 gives the option for metal or wood panel fence. On DWG 607-20 only 2x6 wood panels are used to span the gap. Can the 2x6 wood panels be screwed or drilled into the metal fence posts?
Answer
Submitted: Monday 22-JUN-2026 01:38 PM
For the bid items Farm Fence-Panel/Single(Double) FM, the FM indicates metals panels. Install steel double panels at R/W breaks
offsetting the center post one foot to either side so that the property monument will not be disturbed.  This method eliminates the need for any 2x6 material across the gaps.

202 - SF 169 CONRAD & 2ND INTX-KAL - June 25, 2026

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Wednesday 24-JUN-2026 08:35 AM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:20 PM
New Federal Wage Rates, General Decision Number MT20260080, are now in effect and hereby replaces General Decision Number MT20260079 found in the advertised proposal: WAGE RATES

-2-
Submitted: Monday 22-JUN-2026 12:40 PM
The following quantities have been updated. An amendment will be issued; updated bid files will be posted.

Updated quantity: 614010046 DSGN & CNST MSE WALL-MODULAR BLOCK, Quantity: 130.9 SQYD
Sheets 10, 11 and 18 have been updated: UPDATED SHEETS

Updated quantity: 603017040 STORM DRAIN PIPE-12 IN, Quantity: 238.6 LNFT
Updated quantity: 604010352 ADDITIONAL BARREL 48 IN, Quantity: 12.0 LNFT
Sheets 20-25, 54 and 56 have been updated: UPDATED SHEETS


Questions

-1-
Submitted: Wednesday 17-JUN-2026 07:57 AM
Company: Montana Fence Company
Contact: Jim Ritter
Regarding Item Number 557010105 PEDESTRIAN RAIL: written spec 25.3.e states "Pedestrian rail shall comply with the requirements of AASHTO LRFD Bridge Design Specifications, Section 13.8". Railing that complies with this spec do not rack and cannot follow a slope. The profile of the retaining wall on this project shows that there is up to a 9.11% slope. We recommend railing that complies with IBC/ASC loading requirements rather than the AASHTO LRFD Bridge Design spec. This type of railing will rack and follow the required slope for this project. Ameristar's railing product - Montage Plus meets the IBC/ASC requirement of: "Either a uniform load of 50 lb/ft (applied in any direction) or a concentrated point load of 200 lbs (applied at any point in any direction)." which is the same as the AASHTO LFRD Bridge Design spec and is rackable. Please advise.
Answer
Submitted: Monday 22-JUN-2026 10:50 AM
Special Provision #25, Pedestrian Rail has been updated: PEDESTRIAN RAIL SPECIAL

-2-
Submitted: Wednesday 17-JUN-2026 08:40 AM
Company: Schellinger Construction Co., Inc.
Contact: Grant Roberts
With all of the mainline plant mix receiving a seal and cover would MDT consider changing the plant mix to Grade S 1/2"?
Answer
Submitted: Monday 22-JUN-2026 09:00 AM
Commercial Mix 3/8 IN PG 58V-34 is hereby changed to Commercial Mix ½ In PG 58V-34.  An amendment will be issued; updated bid files will be posted. Sheets 2, 17, and 33 have been updated to reflect this change: UPDATED SHEETS

Remove Item:   401020155 COMMERCIAL MIX-3/8 IN-PG 58V-34, Quantity: 622 TON
Add Item:          401020162 COMMERCIAL MIX-1/2 IN-PG 58V-34, Quantity: 622 TON

-3-
Submitted: Thursday 18-JUN-2026 04:17 PM
Company: White Resources Group, Inc.
Contact: Estimating
608010018 SIDEWALK-SPECIAL DESIGN - this Item looks to be very expensive - would the Department consider an 8" reinforced exposed aggregate finish instead of the embedded river rock? Sheet 29 - Reinforced Sidewalk Detail - To confirm, this is the detail for any of the reinforced concrete? (i.e. 6" reinforced, 8" Special Design-embedded river rock- and 9" reinforced) SP 27 - Clarify Class DP for the Portland Cement Concrete Pavement;
Answer
Submitted: Monday 22-JUN-2026 11:18AM

1. The Embedded River Rock detail was an item developed in coordination with the City of Kalispell for the buffer between the street and the sidewalk.  It will remain as advertised.

2. Sheet 29 – Reinforced Sidewalk Detail. This is for thicker sidewalk and driveway shown with cross hatching and note “6” CONC. SIDEWALK” on Sheet 39 & 40.  

3. Special provision #27, Integral Colored Decorative Concrete Pavement is linked and has been updated. Special Provision 27.B(1) is revised to: Furnish concrete in accordance with Section 551 for Class Pave Concrete. UPDATED SPECIAL

-4-
Submitted: Friday 19-JUN-2026 12:58 PM
Company: Schellinger Construction Co., Inc.
Contact: Grant Roberts
Please post the special provision for the Exploratory Excavation item.
Answer
Submitted: Monday 22-JUN-2026 10:45 AM
The linked Exploratory Excavation special provision is hereby incorporated into this contract: EXPLORATORY EXCAVATION

-5-
Submitted: Friday 19-JUN-2026 04:09 PM
Company: Mountain West Holding Company
Contact: Chris Connors
Please clarify some details for the signing on this project. The only bid item for the posts is Posts Tubular Steel. Plan page S1 identifies the posts as Posts Tubular Steel (Square Perforated). The plans show Round 3" Pipe for all locations but one that shows the perforated tubular (telesapar). The plans do not identify what type of breakaway is to be used for any location and calculation of pounds per location does not appear to be correct depending on what type of breakaway is required. Please complete the signing plans, add the appropriate bid items, and correct the calculations to provide an accurate bid quantity for each item.
Answer
Submitted: Tuesday 23-JUN-2026 3:35 PM
Sign Plans have been updated: SIGN PLANS
Sign calculations can be found here: SIGN CALCS
Updated Sheet 18 can be found here: UPDATED SHEET 18

The following Bid Items have been revised:

619 010 090 SIGNS-ALUM REFL SHEET XI, Quantity: 185.0 SQFT
619 010 300 POSTS–TUBULAR STEEL, Quantity: 1,122.0 LB
620 013 000 STRIPING-WHITE PAINT, Quantity: 1.9 GAL
620 013 960 STRIPING-WHITE EPOXY, Quantity:  1.9 GAL
620 014 000 STRIPING-YELLOW PAINT, Quantity: 9.5 GAL
620 014 960 STRIPING-YELLOW EPOXY, Quantity: 9.5 GAL

The following Bid Items are hereby added to the contract:

619 010 340 POSTS–TUBULAR STEEL-SQ-PERF, Quantity: 1,360.0 LB
619 010 740 FRANG SIGN POST BKWY-3 IN RD, Quantity: 8 EA
619 010 770 SQ TUBLR SLIP BASE BKWY-3 IN, Quantity: 3 EA

An amendment will be issued; updated bid files will be posted.

203 - SLIDE REPAIR-W OF BEARCREEK - June 25, 2026

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Tuesday 23-JUN-2026 01:43 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:20 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES

-2-
Submitted: Monday 15-JUN-2026 03:17PM
The files linked below represent as-built drawings. MDT provides them for informational purposes only. They do not include drawings for modifications and may not completely represent current conditions.  Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project.  The contractor should not rely solely on the as-built drawings provided for bidding purposes nor does any data in these files supersede the data in the contract documents. WATERMAIN AS-BUILTS
 

-3-
Submitted: Friday 19-JUN-2026 03:39 PM
The following quantities have been updated:
622011022 SUBSURFACE DRAIN FILTER HIGH SURV QTY 588.0 SQYD
301020348 DRAIN AGGREGATE QTY 116.1 CUYD
603000050 GRANULAR BEDDING MATERIAL QTY 34.3 CUYD
 
Plan Sheets 4 and 7 and Cross Section Page 1 – Page 22 have been updated: Link
 
An amendment will be issued; updated bid files will be posted.
 


Questions

-1-
Submitted: Monday 15-JUN-2026 11:10 AM
Company: Knife River
Contact: Grant Clingingsmith
Can MDT post the design files, mass diagram, dirt runs, and any additional geotechnical information
Answer
Submitted: Monday 15-JUN-2026 04:13 PM
Linked are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries.  There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner.  Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files.  It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued.  Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.).  The documents can be found at the following link: GEOTECH REPORTS

-2-
Submitted: Tuesday 16-JUN-2026 04:16 PM
Company: Knife River
Contact: Grant Clingingsmith
Can MDT post the design files used for this project?
Answer
Submitted: Wednesday 17-JUN-2026 01:17PM
The design files for the requested project are posted here: DESIGN FILES
The requested files do not represent the staked project, but are only design files.  The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.

In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.

-3-
Submitted: Thursday 18-JUN-2026 11:53 AM
Company: Martin Construction Inc
Contact: Jim Ouldhouse
There is no bid item for clearing and grubbing is this to be incidental to other bid items?
Answer
Submitted: Friday 19-JUN-2026 12:47PM
Clearing and grubbing is to be incidental to the Excavation-Unclassified bid item.

-4-
Submitted: Thursday 18-JUN-2026 11:58 AM
Company: Martin Construction Inc
Contact: Jim Ouldhouse@martinnd.com
Special Provision 22, Coal Waste, has the Department Identified an area for the disposal of Coal Waste?
Answer
Submitted: Friday 19-JUN-2026 12:51PM
Contractor is responsible for finding a location to waste any coal encountered in accordance with Special Provision 22 COAL WASTE.

 

-5-
Submitted: Thursday 18-JUN-2026 12:09 PM
Company: Martin Construction Inc
Contact: Jim Ouldhouse
Special Provisions 2, Unusually severe weather is not considered as a delay cause, Special provision 19 C2a, states that the Project Manager will suspend grading operations during inclement weather if it is determined that that the conditions are unsuitable for continued operations. If this is the case will a suspend work order be issued and will the completion date be extended?
Answer
Submitted: Monday 22-JUN-2026 11:05 AM
This is a completion date contract.  The completion date will not be extended for inclement or unusually severe weather.  In accordance with Special Provision 19, the Project Manager may suspend work for safety reasons if slope stability becomes apparent during or after a rain event.  The completion date will be extended for authorized work suspensions under these conditions in accordance with 108.07.1.

The contract completion date has been revised to December 18, 2026.

Special Provision #2 CONTRACT TIME – COMPLETION DATE has hereby been replaced with Special Provision: CONTRACT TIME – COMPLETION DATE.

-6-
Submitted: Thursday 18-JUN-2026 03:06 PM
Company: Mountain West Holding Company
Contact: Chris Connors
The project requires temporary barrier to separate traffic from the work in the slide area. Special provision 23 states that during working hours, a 12ft lane with a 2ft shoulder must be maintained. Please confirm that it is the Department's position that the 12ft lane and 2ft shoulder will also remain in place during non-working hours while construction requires temporary barrier.
Answer
Submitted: Friday 19-JUN-2026 02:55 PM
Temporary Barrier Rail and Temporary Impact Attenuators have been removed from the project. During working hours maintain a minimum 12-foot travel lane with a 2-foot shoulder. Outside of working hours open the roadway to two-way traffic.

The following bid items have been removed:
618190100 TEMPORARY BARRIER RAIL
606011518 TEMPORARY IMPACT ATTENUATOR

Special Provision #23 TRAFFIC CONTROL/SEQUENCE OF OPERATIONS has been revised: Link

Sheet #5 has been revised: Link

An amendment will be issued; updated bid files will be posted.

204 - I-94 FENCING - TERRY AREA - June 25, 2026

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Tuesday 23-JUN-2026 01:53 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:25 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES


Questions

-1-
Submitted: Friday 29-MAY-2026 07:15 AM
Company: Montana Fence
Contact: Jacob Wutke
Referencing Drawing 607-10 - Combination Woven/Barbed is installed with a double panel every 660ft, At changes in directions, and at Corners. Also there is no detailed Drawing for a metal right away break in which case the state has offset a double on one side of the monument pin. Would the state adjust the quantities of Doubles and Singles for both Metal and Wood due to the fact that the the quantities of doubles and singles is currently inaccurate. On All past jobs double panels far exceed the number of Single Panels. Our Quick Estimation taking a look at the Plans is roughly: (F3M-32IN WW) Doubles - 269 Doubles and 56 Singles with 93 Right away Breaks; (F3W-32IN WW) Doubles -20 and Singles -4 with 4 Right away Breaks.
Answer
Submitted: Monday 8-JUN-2026 03:20 PM
Install a double fence panel at all right of way breaks offset 1 foot onto MDT’s right of way. Quantities for the following bid items are hereby amended per the updated summary:

UPDATED PLAN SHEET 3

607100360      FARM FENCE-PANEL/SINGLE FW              EACH   4
607100362      FARM FENCE-PANEL/SINGLE FM              EACH   101
607100380      FARM FENCE-PANEL/DOUBLE FW            EACH   23
607100385      FARM FENCE-PANEL/DOUBLE FM            EACH   396

An amendment will be issued; updated bid files will be posted.

-2-
Submitted: Friday 29-MAY-2026 07:21 AM
Company: Montana Fence
Contact: Jacob Wutke
In regards to the Portion on Page 8 Concerning Bald Eagles:
"The specific construction activities required for construction of the new right-of- way fence along I-94, between R.P. 178.1 and R.P. 180.1 along I-94 in Prairie County are excepted from this restriction."
Did the State mean Exempted
Answer
Submitted: Wednesday 03-JUN-2026 08:28AM
While exempted or excepted may be used in this situation, the intent of the special is to allow the construction activities for the fence work to commence without any timing restrictions for the BGEPA between RP 178.1 and 180.1.  The contractor will still not be allowed to build man camps or stage material within that area. The timing restrictions in the MBTA special provision for this Project must still be adhered to.

-3-
Submitted: Thursday 04-JUN-2026 08:59 AM
Company: Montana Fence
Contact: Jacob Wutke
In regards to the railroad Flagging and being in the right away- Is the state going to require rail road protective insurance? If So- is this to be figured into our bid or will it be reimbursed in or out of the bid?
Answer
Submitted: Monday 08-JUN-2026 09:15 AM
Railroad Protective and Liability Insurance is required for this project.  This can be provided with a separate company policy, or the contractor can choose to go under the RR’s Blanket policy.  Per the special provision MDT will reimburse the fee for the cost of the permit.

205 - MALTA-EAST - June 25, 2026

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:25 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES


Questions

No Questions available for this project.

206 - MILES CITY-WEST - June 25, 2026

Notifications

No Notices available for this project.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Tuesday 09-JUN-2026 01:30 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES


Questions

No Questions available for this project.

207 - S-482 REPAIR - S OF LIBBY - June 25, 2026

Notifications

No Notices available for this project.


Amendments

-1-
Submitted: Tuesday 23-JUN-2026 02:03 PM
An Amendment has been posted for this project: AMENDMENT
To download the amendment bid files: Bid Express™ Secure Internet Bidding


Clarifications

-1-
Submitted: Wednesday 24-JUN-2026 03:40 PM
Special No. 22 STREAM RESTORATION SPECIALIST (SRS) is rescinded.

Special No. 45 BIOENINGEERED BANK, is rescinded. 
The Special Provision BIOENGINEERED BANK is hereby incorporated into the contract.


Questions

-1-
Submitted: Thursday 11-JUN-2026 02:55 PM
Company: Battle Ridge Builders
Contact: Cody Ham
Beams suppliers are saying these beams can't be delivered until December. With a December delivery, holidays and Coldweather concreting on the superstructure, please extend the completion date to April 15 - 2027.
Answer
Submitted: Wednesday 17-JUN-2026 07:30 AM
MDT’s intention is to expedite the completion of this project and minimize, to the greatest extent possible, the inconvenience to the community being effected by the closure of this bridge. The completion date is hereby changed to February 26, 2027, and revised incentive language incorporated into the contract. 

The following Special Provisions are rescinded:
No. 2 CONTRACT TIME – COMPLETION DATE
No. 4 CONTRACT TIME – INCENTIVE & DISINCENTIVE MILESTONE
No. 5 SEQUENCE OF OPERATIONS

The following Special Provisions are hereby incorporated into the contract:
CONTRACT TIME – COMPLETION DATE
CONTRACT TIME – INCENTIVE MILESTONE
SEQUENCE OF OPERATIONS


UPDATED: 17-JUN-2026 04:06 PM
UPDATED CONTRACT TIME – COMPLETION DATE

-2-
Submitted: Monday 15-JUN-2026 09:45 AM
Company: Sletten Construction
Contact: Russ Robertson
In addition to what Battle Ridge asked. With the requirement for temporary facilities to access and build this project, we are at least 60-80 days out from award for a 404 permit after MDT reviews and approves our permit application. Even with the beams delaying the project, permitting would have made it impossible to meet the requirements of the contract. Instead of extending time to April, why not make it more realistic and extend until June so that we don't have to heat the deck concrete and so we can pave with temperatures that meet the Standard Specifications?
Answer
Submitted: Wednesday 17-JUN-2026 08:00 AM
Please see the response to Question #1

-3-
Submitted: Monday 15-JUN-2026 03:07 PM
Company: Knife River Prestress Inc
Contact: James Ryan Moss
With the quick turnaround of the prestressed girders for this project, we respectfully request the agency to drop the 800 lb. maximum limit of cement content in order for the girders to achieve concrete strength in a timelier manner and enable early shipping if requested.
Answer
Submitted: Tuesday 16-JUN-2026 03:37 PM
Project-specific mix design parameters will be evaluated once a contractor is selected and the construction schedule is established. At that time, MDT can assess whether the proposed concrete mix meets the required performance criteria and overall objectives for the project.

-4-
Submitted: Wednesday 17-JUN-2026 08:20 AM
Company: Sletten Construction
Contact: Russ Robertson
Due to the exigent nature of this project, will MDT shorten their submittal review period to 7 calendar days for all submittals and 5 calendar days for all resubmittals to ensure that contractor has the best chance to meet the milestones of the project?
Answer
Submitted: Thursday 18-JUN-2026 01:25PM
MDT is fully committed to prioritizing the review and processing of all submittals as promptly as practicable to support timely completion of this project.

 

-5-
Submitted: Wednesday 17-JUN-2026 08:47 AM
Company: Sletten Construction
Contact: Russ Robertson
Due to the water need for transverse deck grooving, if low temperatures are encountered, it could make this impossible to accomplish in the winter. Could transverse deck grooving be incorporated into the Spring 2027 activities along with the silane sealer? This work should be able to be completed under single lane traffic. It would require a few extra working days to be added.
Answer
Submitted: Wednesday 17-JUN-2026 04:05 PM
The bridge transverse grooving and silane sealer activities for the bridge deck can be completed outside of the substantial completion window to align with favorable weather conditions.  5 additional working days will be added to the contract for a total of 15, for these items and those stated in updated Special Provision CONTRACT TIME – COMPLETION DATE posted in response to Question #1.

-6-
Submitted: Thursday 18-JUN-2026 12:13 PM
Company: Sletten Construction
Contact: Ian McIntosh
The current pipe pile coating specification requires the finish coat to be applied in the field after the piles have been driven and placed in their final position. Given the seasonal restrictions and anticipated weather conditions during construction, please consider allowing the finish coat to be shop applied prior to shipment. Due to the project schedule, it is likely that field conditions will not consistently meet the temperature requirements necessary for proper application of the finish coat. Any damage to the coating resulting from handling, transportation, or pile driving could be repaired with touch-up paint in accordance with the manufacturer's recommendations once weather conditions are suitable. Will MDT consider allowing the finish coat to be shop applied, with field touch-up performed as necessary after installation?
Answer
Submitted: Thursday 18-JUN-2026 02:49PM
MDT will allow the finish coat on the piles to be shop applied prior to shipment, with field touch-up repairs performed as needed after installation in accordance with the manufacturer’s recommendations.

 

-7-
Submitted: Thursday 18-JUN-2026 02:40 PM
Company: Sletten Construction
Contact: Ian McIntosh
With this project being scheduled for construction during the winter months, Special Provision 31, Girder Temperature Requirements for Fixed Shoe Welding, is a concern. Based on the anticipated construction schedule, there is potential that ambient temperatures may not exceed 40°F during much of the period in which this welding will be performed. As currently written, the specification may require extensive heating and protection measures for each girder to maintain compliance with the temperature requirements. Please clarify whether MDT intends to strictly enforce the girder temperature requirements throughout this period or if flexibility will be provided given the seasonal constraints of the project. This clarification will allow us to properly account for these requirements in our bid.
Answer
Submitted: Monday 22-JUN-2026 03:36PM
Girder temperature requirements for fix shoe welding will be enforced.  If temperatures do not align with the specification at the time the contractor is scheduled for fix shoe welding, alternative measures such as temporary bracing, clamping, or other stabilizing methods may be used to keep the project moving forward.  Welding to commence when the temperature requirements can be met.  Compensation for this additional work will be made in accordance with 109.04.  Time extensions for schedule delays will be in accordance with 108.07.


Miscellaneous-Work has been increased to 75,000 units.  An amendment will be issued;updated bid files will be posted.

301 - NEVI PROGRAM - INTERSTATE SYSTEM - July 29, 2026

Notifications

-1-
Submitted: Wednesday 18-MAR-2026 11:00 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on April 7, 2026.

Project Name: NEVI Program- Interstate System
Project No: EV STWD(983)
Control No: 10436000


Project Description:
The Project consists of performing all services necessary to design, construct, operate, and maintain EV charging stations in compliance with the requirements described in the draft Contract included as Attachment 2. The EV charging stations will be located along Montana’s AFCs at locations to be determined by Proposers as described in the draft RFP included as Attachment 1. The work generally includes the following:
• Design and construct a minimum of four network-connected direct current (DC) 150 kilowatt (kW) charging ports, at each EV charging station, capable of simultaneously and continuously charging four EVs, located within approximately a one-mile driving distance of an AFC, and available for use by the public 24 hours per day, seven days per week, and year-round.
• Operate and maintain the EV charging infrastructure for a minimum of five years following EVSE Acceptance pursuant to Section 4.6.4 (EVSE Acceptance) of the Contract in accordance with the O&M Period requirements.
• Provide secure payment methods.
• Collect, process, retain, and share near real-time and static data.
• Provide a minimum of 20 percent of Eligible Project Cost.

The project RFQ and attachments can be found at the following link: RFQ-ATTACHMENTS

-2-
Submitted: Monday 23-MAR-2026 11:36 AM
MDT is hosting an SOQ Webinar at 11:00 am Mountain Time on March 25, 2026, to highlight important components of the RFQ. This informational webinar is open to the public with microphone and video disabled. All questions should be asked through the Q&A Forum in accordance with the RFQ and no questions will be answered during the webinar.
Topic: MDT SOQ Webinar
Time: Mar 25, 2026 11:00 AM Mountain Time (US and Canada)

Join Zoom Meeting
https://mt-gov.zoom.us/j/86089197890?pwd=3zMC8YUcouEzfTThbQAWgacDDVV5lS.1

Meeting ID: 860 8919 7890
Password: 590639

Dial by Telephone
+1 646 558 8656
Meeting ID: 860 8919 7890
Password: 590639
Find your local number: https://mt-gov.zoom.us/u/kbzpCWQBMV

-3-
Submitted: Wednesday 25-MAR-2026 08:35AM
Update to the Personnel Experience Section 3.4 of the RFQ:
The Personnel Experience portion of the SOQ shall not exceed 16, 8.5”x11” pages (two pages maximum for each of the eight resumes). Personnel Experience is a scored element with a scoring total score of 300 points.

-4-
Submitted: Thursday 26-MAR-2026 07:36 AM
NEVI Program SOQ PowerPoint and Webinar: NEVI SOQ

-5-
Submitted: Tuesday 14-APR-2026 11:40 AM
In lieu of the email mdtalternativecontracting@mt.gov provided in Section 2.3: SOQ Submittal of the RFQ, please submit SOQ’s through the file transfer service to Eric Parrish at eparrish@mt.gov and Aubrey Yerger at ayerger@mt.gov. The email (mdtalternativecontracting@mt.gov) appears to be invalid when used with the state file transfer service.

-6-
Submitted: Wednesday 13-MAY-2026 11:13 AM
Shortlisted Firms ( In alphabetical order):
EV Gateway
FTI & SWTCH
Love’s Travel Stops

-7-
Submitted: Thursday 04-JUN-2026 12:23PM
The following attachments to the RFP have had issues opening properly:

  • 10436_02_A1_1B_HazMat.pdf
  • 10436_02_A1_1C_CatEx.pdf

Working files can be found here: RFP Attachments Working

It should be noted that the files will not open properly in the Microsoft Explorer or Google Chrome Browsers. You will need to right click and force them to be opened with Adobe Acrobat.


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 26-MAR-2026 11:38AM
The SOQ submittal date posted to the Q&A forum is hereby amended to April 15th at 11:00 a.m. local time to align with the procurement schedule in the RFQ.

-2-
Submitted: Tuesday 07-APR-2026 11:56AM
The Preproposal meeting has been rescheduled for Tuesday, May 26th, 2026, from 12:30 PM to 1:30 PM local time.

-3-
Submitted: Friday 10-APR-2026 08:34AM
The introduction (Page 1, Paragraph 3) of the RFQ is hereby modified as follows:

“Proposers may elect to pursue one, multiple, or all a minimum of three EV charging stations identified in the subsequent Request for Proposals (RFP). Following evaluation of the Statement of Qualifications (SOQs), MDT will identify a shortlist of Proposers that will receive an RFP and may submit a Proposal to MDT. After evaluation of Proposals, Montana Transportation Commission (MTC) will select one NEVI Contractor, and MDT will enter into one three or more EV charging station-specific agreements with the NEVI Contractor. “

-4-
Submitted: Thursday 23-APR-2026 09:16 AM
In support of Q&A clarification #3 the following definition applies:

In accordance with 23 CFR 680.104, EV charging station means the area in the immediate vicinity of a group of chargers and includes the chargers, supporting equipment, parking areas adjacent to the chargers, and lanes for vehicle ingress and egress. A charging station could comprise only part of the property on which it is located.

-5-
Submitted: Thursday 28-MAY-2026 12:35 PM
The following edits are to section 3 Proposal Content Requirements, subsection 3.3 Price Proposal of the RFP:

  • Proposer shall enter the NEVI Contractor Share Contribution (%$) for each EV charging station. The NEVI Contractor Share (%) will be automatically calculated. This percentage must be 20% or higher.
  • Federal Share of Eligible Costs must not exceed $800,000 for each EV charging station.
  • All percentages must be Share of Eligible Costs whole numbers.

-6-
Submitted: Monday 01-JUN-2026 10:52 AM
The Q&A Forum close date is amended in section 2, subsection 2.2 -  Procurement Schedule of the RFP as follows:

June 30,  July 1, 2026  Q&A Forum Closes at 5:00 p.m. local time

-7-
Submitted: Thursday 18-JUN-2026 08:25 AM
Section 2.5.2 Price Proposal Submittal (Page 5, Paragraph 3) is hereby modified as follows:

Additionally, the Proposer shall submit a Proposal Guaranty in an amount not less than 10% of the price proposed in the Proposer’s Price Proposal.Total Project. Cost Proposal shall accompany each Proposer’s Total Project Cost Proposal. The Proposal Guaranty shall must accompany the Proposer’s Price Proposal and be in the form of a surety bond, payable to MDT. The surety issuing the Proposal Guaranty on any proposal bond shall be a company recognized authorized to execute bid bonds for contracts of the Federal Government. The Proposal Guaranty shall secure the stand for the Proposer’s obligation to timely and properly satisfy all conditions precedent to execution of the Contract and execute the Contract.
 


Questions

-1-
Submitted: Thursday 19-MAR-2026 09:18 AM
Company: MN8 Energy
Contact: Brianna Alix
Within the RFQ, it is outlined that there will be an SOQ webinar held on 3/25. Could you please share how we should register for the session?
Answer
Submitted: Monday 23-MAR-2026 11:29 AM
MDT will post the SOQ webinar information as a notification to the Q&A Forum.

-2-
Submitted: Monday 30-MAR-2026 12:59 PM
Company: Voltpost
Contact: Olivia Cosio
Is MDT only interested in DCFC along AFCs? Can these federal funds also go towards Level 2 chargers at the zones outlined in the RFP?
Answer
Submitted: Wednesday 01-APR-2026 08:25 AM
This project will not offer funding for AC level 2 charging ports.

-3-
Submitted: Wednesday 01-APR-2026 08:31 AM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
1. Does the applicant have to apply under joint venture if the EVSE provider is a contractor on the project? Or can we just provide the letter of commitments for them?
2. Can we include cover pages? If so, does that count towards the max page amount limit?
3. Does the percentage of their contributions on a project have to be on the key personnel resume?
4. Do we have to register prior to submission of the SOQ?
5. Does the form have to stay within their individual page limit? For example, if form a is 1 pg, form b is 3pgs, form c is 1 pg, not exceeding 5pgs in total does that suffice?
Answer
Submitted: Thursday 2-APR-2026 03:29PM
1. No, Proposer does not have to propose as a JV. The Proposer can propose as a single entity led by a prime with subcontractors or a JV. If the Proposer intends to form a JV, but has not yet done so, the Proposer can provide a signed letter of intent or teaming agreement stating intent to form a JV if awarded.
2. A cover page may be included for the whole proposal and a cover page to separate each section outlined in the RFQ. These sheets will not count towards the max page limit.
3. No, the percentage contribution/time spent on a particular project doesn’t specifically need to be included on the key personnel resume.
4. Per section 3.4 of the RFQ,"the EVSE Contractor and any other team memeber that will perform construction or installation is required to be a licensed contractor in the state of Montana prior to the execution of the Contract."
5. The Max Pages in scoring table 4.2.1 should be followed for page limits. Each form and section should not exceed the designated page limits.

-4-
Submitted: Monday 13-APR-2026 03:46 PM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
Per the RFQ it states to send the submission to mdtalternativecontracting@mt.gov. However, it states that email is invalid and gives an error. If the submission is sent to the two contacts listed in the RFQ Eric Parrish and Aubrey Yerger, is the submission considered valid and properly submitted?
Answer
Submitted: Tuesday 14-APR-2026 07:17 AM
Yes, the submission received via email to Eric Parrish (
eparrish@mt.gov) and Aubrey Yerger (ayerger@mt.gov) is considered valid.

-5-
Submitted: Tuesday 14-APR-2026 07:46 AM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
Are applicants required to acknowledge the clarifications?
Answer
Submitted: Wednesday 15-APR-2026 03:17 PM
Clarifications are considered to be part of the Q&A. Therefore, acknowledgement of the Q&A, as indicated in Section 3.2.1 of the RFQ, is acknowledgement of the clarifications.

-6-
Submitted: Tuesday 16-JUN-2026 09:45 AM
Company: Love's Travel Stops & Country Stores, Inc
Contact: Paris Despenza
1. In reference to 2.5.2 it states we shall provide surety bond guaranty not less than 10% of the total project amount and that it shall accompany each proposer total project cost proposal. Is that being submitted through bidexpress with the price form or attached to the tech proposal? Will we need a surety bond per station?
2. In reference to 3.1, we are required to submit the notarized statement from an admitted surety to identify proposers with available bonding capacity. Is this different than the surety bond guaranty we have to submit with the Admin proposal? Please clarify.
3. For the Environmental NEPA evaluation, is the NEPA forms consist of 1A-1D during application process? Some of the questions from the HAZMAT and CATEX looks repetive for to 1A and 1D. Please provide clarity which forms are needed to be filled out during application process. If so for the HAZMAT and CATEX, it ask for control number, project number, project name, where do we find that information? Are we needing to send these forms to an specific consultant?
4. In addition to form 1B, it asks for UPN, design lead etc. Where do we get that information? Also are we required to attach photos? If so what type of photos?
5. For the American Land Form, are we required to provide the utility correspondence, deed along with site host letter? Or is any of those documentations sufficient for the American Land Title Form?
6. Is utility outreach documentation required during the application process or only post award?
Answer
Submitted: Thursday 18-JUN-2026 08:20 AM
1. The Proposal Guaranty shall be submitted through Bid Express with the Proposer's Price Proposal. A single Proposal Guaranty is required by each Proposer and shall be in an amount equal to ten percent (10%) of the aggregate price proposed in Proposer’s Price Proposal for all Sites included in the Proposer's submission. A separate Proposal Guaranty is not required for each Site.

2.MDT will accept the letter of bonding capacity submitted with the proposer’s SOQ, provided it is notarized and identifies the proposer's available bonding capacity. This requirement is separate from the Proposal Guaranty. In addition to the notarized letter of bonding capacity, each Proposer shall submit a Proposal Guaranty in an amount equal to ten percent (10%) of the Proposer's submitted Contract Price, which secures the Proposer's proposal in accordance with the solicitation requirements.

3.The NEPA document for the project is Appendix 1 Form 1C [Categorical Exclusion (CE) Documentation]. Appendix 1 Forms 1A (Biological Resources Report) and 1B (Initial Site Assessment) provide the supporting information for the findings and conclusions documented in Form 1C. Forms 1A, 1B, and 1C are all required and all need to be completed in their entirety.

Appendix 1 Form 1D (Aquatic Resources Technical Memo) is not a NEPA document. This form is provided for use by the Proposer if the Proposer identifies that there are wetlands or waters on or adjacent to the project. This form only needs to be completed in its entirety if there are aquatic resources on or adjacent to the project.

For these forms the project info is as follows:
Project Name: NEVI PROGRAM-INTERSTATE SYSTEM
Project Number: EV STWD(983)
Control Number: 10436000

Sending these forms to a specific consultant is not a requirement. However, the person who fills the Environmental Compliance Lead position on a proposer’s team must meet the requirements of section 4.2.9 Environmental Compliance Lead of the RFP.

4.For Appendix 1 Form 1B, the UPN is the same as the Control Number. The design lead would be the individual leading the design efforts at the Design Firm (identified in the Proposers SOQ). There is no requirement to include attachments or photos; the Proposer determines if these are needed.

5.The American Land Title Association (ALTA) form(s) used should verify that the person identified in question B1 is the legal owner of the property where the proposed EV station will be installed. Evidence should also be provided that the utility easements necessary to provide electricity to the EV charging station are in place whether that is an ALTA form or correspondence with a utility is left up to the Proposer.

6.No specific utility documentation is required during the proposal process.

302 - GREYCLIFF AREA BRIDGES - September 09, 2026

Notifications

-1-
Submitted: Wednesday 29-APR-2026 09:24 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on May 27, 2026.

Project Name: GREYCLIFF AREA BRIDGES
Project No:      STPB 81014(2)0
Control No:      10661000

Project Description:
The scope of work for this Design-Build Contract includes services required to design and reconstruct six (6) existing bridges along Highway 10 between Greycliff and Big Timber, Montana.  The Project involves replacing the aging and deteriorating bridges with new structures and will reconstruct the adjacent roadways as necessary.

The project RFQ and attachments can be found at the following link: RFQ AND ATTACHMENTS

-2-
Submitted: Wednesday 24-JUN-2026 12:58 PM
Short-listed Firms (in alphabetical order)

Battle Ridge Builders and Forsgren
Frontier West and Morrison-Maierle
Jackson Contractor Group and Interstate Engineering


Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Monday 11-MAY-2026 02:55 PM
Addition to Section 1., paragraph 2 of the RFQ: When the system prompts the user to enter a delivery email, complete the following steps to submit the SOQ to mdtalternativecontracting@mt.gov:   Select the “Find a State Group” tab, type “MDT Alternative Contracting” in the search bar, click the “Search” button, click the “+MDT Alternative Contracting” button after the search has completed, click the “Send” button.


Questions

-1-
Submitted: Friday 08-MAY-2026 02:39 PM
Company: Morrison-Maierle
Contact: Luke Carlson
Can the table that defines which Phase 1 Documents are Bridging Documents and which are provided for informational purposes only be provided now, so firms can assess the required design effort, the relative value of the stipend, and the ability to meet the project completion date?
Answer
Submitted: Tuesday 12-MAY-2026 03:41PM
The table that defines which Phase 1 Documents are Bridging Documents is being developed and not available. The following is a preliminary list of Bridging Documents that will be provided with the RFP: Preliminary Geotechnical Field Investigation Report, Categorical Exclusion, Scope of Work Report, SHARES Reports and Hydraulic Models, Control Survey, Cadastral Survey, Engineering Survey, and Structure Type, Size and Location Report. The contractual Bridging Documents will be identified and provided with the RFP and will supersede the preliminary list provided within this response.

-2-
Submitted: Friday 08-MAY-2026 02:36 PM
Company: Morrison-Maierle
Contact: Luke Carlson
Will MDT entertain Alternative Technical Concepts to allow teams to best meet MDT design requirements and project goals?
Answer
Submitted: Tuesday 12-MAY-2026 03:55PM

Alternative Technical Concepts are not allowed on this project. Proposed deviations from the Contract requirements must be submitted as questions through the Q&A Forum.

-3-
Submitted: Friday 08-MAY-2026 03:41 PM
Company: Frontier West LLC
Contact: Kris Anderson
Would MDT consider extending the duration between the release of the RFP and the technical proposal due date timeline if the Phase 1 work does not include roadway or bridge design or plans?
Answer
Submitted: Tuesday 12-MAY-2026 04:02PM
The Phase 1 Documents will include a preliminary road plan and profile sheet for each site. The associated electronic CAD files will be provided with the Phase 1 Documents attached to the RFP.  The draft RFP requires the Firm to only submit a road plan and profile sheet for each site with the Technical Proposal.  The Tentative Schedule of Events within the RFQ is unchanged.

-4-
Submitted: Friday 08-MAY-2026 03:41 PM
Company: Frontier West LLC
Contact: Kris Anderson
The preliminary drawings provided with the RFQ do not appear to provide any bridge or roadway design information. Will MDT increase the stipend if the Phase 1 work does not include roadway and bridge plans and design?
Answer
Submitted: Tuesday 12-MAY-2026 04:05PM
The Phase 1 Documents will include a preliminary road plan and profile sheet for each site and the associated electronic CAD files. The stipend will not be increased.

-5-
Submitted: Friday 15-MAY-2026 12:01 PM
Company: Forsgren Associates
Contact: Nathan Haddick
Section VI. A. 1. g. of the RFQ states: "The prime contractor, design professional, and key personnel (including the individual’s employer) are exclusive to the Firm and cannot team with another Firm to submit more than one SOQ per Project." Does this restriction preclude a subconsultant or subcontractor from being included on multiple teams submitting SOQ's for this project if they are not listed as Key Personnel?
Answer
Submitted: Wednesday 20-MAY-2026 08:25 AM
Individuals assigned as Key Personnel and their employer are exclusive to the Firm and cannot be associated with multiple Firms.  All other companies, besides those assigned with Key Personnel, may team with multiple Firms.

-6-
Submitted: Friday 19-JUN-2026 10:29 AM
Company: Morrison-Maierle
Contact: Luke Carlson
The response to Question 1 in the Q&A states that the Scope of Work Report will be provided. However, we were unable to locate this report in the provided RFP materials. Please guide us on where to find the report or provide it.
Answer
Submitted: Friday 26-JUN-2026 10:48 AM
The response to Question #1 provided a preliminary list of Bridging Documents which included the Scope of Work Report for the Project.  The Scope of Work Report was reviewed by MDT and does not provide any additional design or construction requirements due to the limited design; therefore, it will not be provided to the short-listed Firms.

-7-
Submitted: Friday 19-JUN-2026 02:23 PM
Company: Frontier West LLC
Contact: Kris Anderson
The response to Question 3 states that the plan and profile sheets for each site will be provided with the Phase 1 documents. We are unable to locate the plan and profile sheets in the provided RFP materials. Please provide the plan and profile sheets or let us know where we can find this data within the material provided.
Answer
Submitted: Friday 26-JUN-2026 10:50 AM
The plan and profile sheets for each site are included in pdf format as the last page(s) of the SHARES Reports.  The corresponding CAD files can be found within the following OneDrive folder path: 10661 Greycliff Area Bridges – RFP and Attachments > Attachments > F-Phase 1 Documents > HY > 10661000HYEXZ01.zip.

303 - MILL CREEK HIGHWAY - September 22, 2026

Notifications

-1-
Submitted: Wednesday 15-APR-2026 11:36AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on May 13, 2026.

Project Name: MILL CREEK HIGHWAY
Project No:      SSS 569-1(11)6
Control No:     10473000

Project Description:
The scope of work for this Design-Build contract includes reconstruction of approximately five miles of Secondary Highway 569 (S-569), also known as Mill Creek Highway, from reference post (RP) 6.11 to RP 11.0.  The project is funded by a RAISE grant awarded to Anaconda-Deer Lodge County (ADLC).  The project is intended to address existing deficiencies and improve safety.  The roadway will be reconstructed to include 12-foot driving lanes and 1-foot shoulders.  Additionally, the project will improve roadway geometrics and reconstruct the existing pavement with new bituminous surfacing.  The project will also include new centerline rumble strips, pavement markings, signage, guardrail, improved clear zones and side slopes, and improved hydraulics, culvert and storm water infrastructure.

The project RFQ and attachments can be found at the following link: RFQ AND ATTACHMENTS

-2-
Submitted: Monday 01-JUN-2026 07:06 AM
Short-listed Firms (in alphabetical order)

  • Montana Materials & Construction and KLJ Engineering
  • Riverside Contracting and Morrison-Maierle
  • Schellinger Construction and DJ&A

Amendments

No Amendments available for this project.


Clarifications

-1-
Submitted: Thursday 07-MAY-2026 01:26 PM
Modification to Section I., paragraph 2 of the RFQ:  When submitting SOQ through the File Transfer Service, submit the SOQ to the following email addresses: ayerger@mt.gov and bgraff@mt.gov.  Do not submit SOQ to mdtalternativecontracting@mt.gov


Questions

-1-
Submitted: Monday 08-JUN-2026 11:00 AM
Company: Morrison-Maierle
Contact: Bryan Vanderloos
Can MDT confirm the guardrail type for the project?  The RFP calls out Box-Beam, but the Phase 1 plans show MGS guardrail.
Answer
Submitted: Thursday 11-JUN-2026 07:10 AM
Provide Box Beam Guardrail in accordance with the RFP.