Quick Links:
BULLETIN BOARD
___________________________________________________________________________________________________________________________________________________________________________________
Libby Exigency Project – Shortened Advertising Period
A shortened advertising period for S-482 Repair-S of Libby is scheduled to begin on June 11th, 2026. The Q&A Forum will close to questions at 8 am on June 22nd and the Bid Letting will occur at 9 am on June 25th with award on June 30th. The anticipated Notice to Proceed is July 13th.
___________________________________________________________________________________________________________________________________________________________________________________
Billings Bypass – Johnson Lane Interchange Extended Advertisement (UPDATED 6/1/26)
The BBP – Johnson Lane Interchange is an MDT project in Yellowstone County to reconstruct the Johnson Lane Interchange on Interstate 90. Advertisement for the project is scheduled to begin on July 16th, 2026 running through August 27th, 2026. The Q&A Forum will be open for questions beginning on Thursday, July 16th and will close on Friday, August 21st at 8 am. The Preliminary Bid Package is available on the MDT Contracting & Bidding webpage at the following address: Preliminary-Copy-Proposal-and-Plans
The Q&A Forum period for all other projects in the August 27, 2026 letting will remain unchanged, with the Q&A Forum opening to questions beginning on July 30th and closing to questions on Monday, August 24th at 8 am.
_____________________________________________________________________________________________________________________________________________________________________________________________________________________________
Ekalaka Exigency Project
MT-323 Culvert – S of Ekalaka is an exigency project to replace the failing 108-inch CSP culvert on MT 323 at R.P. 22.9. Due to the risk of failure of the pipe there is a severe threat to the integrity of the roadway and the safety of the travelling public. The project will be included in the scheduled August 6th, 2026 bid letting with advertising beginning on July 9th and award on August 18th. The Notice to Proceed will be expedited and is expected to be on or around August 31st, 2026.
_____________________________________________________________________________________________________________________________________________________________________________________________________________________________
New Q&A Forum Closing Time: Beginning with the April 9th bid letting, the Q&A Forum will close to Contractor questions at 8:00am (previously 10am) on the Monday before bid letting unless it’s a state holiday. Answers provided by the Department to the questions, clarifications, and notifications can be posted up to 5:00 p.m., the day before the bid opening.
____________________________________________________________________________________________________________________________________________________________________________________
Watch - Public Bid Opening - Live Stream: ZOOM MEETING INFORMATION
______________________________________________________________________________________________________________________________________________________________________________________________________________________________
Advertised Projects: If you would like to receive the Invitation for Bids PDF document when projects are advertised, please send an email request to mdtcps@mt.gov. Follow the link for more information: EMAIL DISTRIBUTION
______________________________________________________________________________________________________________________________________________________________________________________________________________________________
101 - OLD HWY 10 BRIDGES E OF HYSHAM - June 04, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Friday 08-MAY-2026 08:35AM
Special provision #3, Sequence of Operations is hereby replaced by the linked updated special provision: SEQUENCE OF OPERATIONS
Questions
-1-
Submitted: Wednesday 13-MAY-2026 03:42 PM
Company: Rinker Materials - Rapid City, SD
Contact: Brian Jenner
The box culvert sloped end sections shown on SHEET NO. 10 show a top slope of 3:1. MDT standard slope is 2:1. Why has the top slope changed? Can the standard slope of 2:1 be used instead?
Answer
Submitted: Friday 15-MAY-2026 01:56PM
1. The standard 2:1 slope is not a traversable slope. Utilizing a 2:1 slope would necessitate guardrail be installed to shield the end of the box culvert.
2. No. The box culverts need to utilize the 3:1 sloped end sections with the pipe runners to shield the ends of the culverts while not requiring the installation of guardrail.
-2-
Submitted: Friday 15-MAY-2026 03:35 PM
Company: Missouri River Contractors
Contact: Kris Anderson
At STA's 204+75-205+05 and 304+50-304+80 temporary shoring is called out 1' inside existing RW on project Left. There is a Fiber Optic line shown very close to that. Will this utility be relocated before the project starts?
Answer
Submitted: Thursday 21-MAY-2026 07:20 AM
Yes, the Fiber Optic line is currently scheduled to be moved further into the railroad right-of-way prior to notice to proceed. Shoring will still be necessary to ensure proposed excavations do not impact railroad right-of-way.
-3-
Submitted: Monday 18-MAY-2026 12:01 PM
Company: Missouri River Contractors
Contact: Kris Anderson
Special provision 28 states that irrigation season is typically begins April 23rd and ends October 10th. It also states supply of irrigation water must be maintained during construction and can't be reduced without written permission. Would MDT consider delaying the NTP to October 12th so work will start outside irrigation season?
Answer
Submitted: Tuesday 26-MAY-2026 09:42AM
Yes, the flex NTP will be moved to October 13th. Special Provision #2 CONTRACT TIME – FLEX TIME PROCEED DATE is hereby replaced with the following special provision: LINK
-4-
Submitted: Friday 22-MAY-2026 09:57 AM
Company: Martin Construction Inc
Contact: Jim Ouldhouse
Special Provision 20 provided a reference to Geotechnical Report, please provide a link to the report.
Answer
Submitted: Tuesday 26-MAY-2026 03:13PM
Linked are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at the following link: LINK
-5-
Submitted: Tuesday 26-MAY-2026 12:02 PM
Company: Beador Construction Company Inc.
Contact: Denise Gutierrez
Please confirm whether there is a DBE goal that should be met.
Answer
Submitted: Thursday 28-MAY-2026 12:16PM
DBE goals are not required for this project.
-6-
Submitted: Tuesday 26-MAY-2026 03:33 PM
Company: Engineered Concrete Products
Contact: Mike Meredith
On the sloped ends of the 18x8 and 12x6 Box culverts, MDT states that the pipe runners and cross beam supports need to meet the Mash Level 3 rating with deflection not exceeding 4". We believe the Mash Level 3 rating is not the proper design criteria. It is my understanding that Mash testing is for guardrails and is/has been tested utilizing a lateral load. Furthermore we would suggest designing the safety grate to carry an HL-93 axle load (vertical load) with impact loading for the structural portions of the safety grate. Please advise.
Answer
Submitted: Wednesday 27-MAY-2026 11:00AM
MDT is not requesting MASH Test Level 3 testing. MDT is requesting the pipe runner assembly pass the MASH Test Level 3 test vehicle, (a two-wheel drive, four-door, half-ton pickup truck, weighing approximately 5,000 pounds) without deflecting more than 4 inches.
-7-
Submitted: Thursday 28-MAY-2026 11:05 AM
Company: COP Construction
Contact: Olivia Adolph
The temporary shoring at Site 2 and Site 3 is designed to be placed one foot inside the right-of-way line, adjacent to the BNSF railway corridor. Section III Page 7 notes that construction within 25 feet of the center of any track requires railroad plan approval and flagging protection. Will MDT coordinate the railroad agreements and cover all railroad flagging fees, or must the contractor include railroad flagging costs and railroad protective liability insurance within their lump sum Temporary Shoring or Mobilization bid items?
Answer
Submitted: Tuesday 02-JUN-2026 09:00 AM
The linked Railroad Coordination and Flagging special is hereby incorporated into this contract. RAILROAD COORDINATION
Flagging is not anticipated to be needed. The contractor will be responsible for coordinating with BNSF’s real estate department, Jones Lang LaSalle, to secure temporary occupancy permit and required insurance provisions.
The agreement can be accessed online at https://bnsf.railpermitting.com. There will be additional fees associated with this process. The Department will reimburse contractor for the approved processing fee. Begin this process upon receipt of Notice of Award as it may take 8 to 12 weeks to complete the process. The Contractor may choose to pay the Rush Fee; however, the Department will only pay regular processing fees. If you need assistance or have questions, contact Melissa Woodruff at (817) 352-1048 or email melissa.woodruff@am.jll.com.
-8-
Submitted: Thursday 28-MAY-2026 11:10 AM
Company: COP Construction
Contact: Olivia Adolph
The Surfacing Table on Plan Sheet 7 lists Crushed Agg. Course with aggregate quantities calculated in tons totaling 692 tons including approach surfacing. However, the Bid Schedule Line 0100 lists Crushed Aggregate Course in CUYD with a quantity of 692.00 CUYD. Please clarify whether the design intent is 692 tons or 692 cubic yards
Answer
Submitted: Thursday 28-MAY-2026 02:08PM
The Surfacing Table on Plan Sheet 7 and the Bid Schedule both list Crushed Agg. Course as the CUYD unit of measurement. The design intent is 692 CUYD.
102 - US 2 EROSION REPAIR HAVRE - June 04, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Monday 11-MAY-2026 04:03PM
Special Provision #18 Clean Water Act Section 404 Permit and Section 401 Certification is hereby replaced with the following updated special provision: LINK
Questions
-1-
Submitted: Tuesday 26-MAY-2026 12:03 PM
Company: Beador Construction Company Inc.
Contact: Denise Gutierrez
Please confirm whether there is a DBE goal that should be met.
Answer
Submitted: Wednesday 27-MAY-2026 08:47AM
There is no DBE goal on this project.
103 - D4 CRACK SEAL NORTH - June 04, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
No Clarifications available for this project.
Questions
-1-
Submitted: Friday 29-MAY-2026 07:03 AM
Company: Z and Z Seal Coating Inc
Contact: Spencer Foster
In reference to Bid Item 403010257 Crack Filling Mastic -
Since no U.S. manufacturer produces ASTM D8260 Type 3 mastic, will MDT grant a non-availability waiver for the BABA requirements for this material? Or will the standard ASTM D8260 Type 1 mastic that has been used in the past and that maintenance division still uses be acceptable?
Answer
Submitted: Friday 29-MAY-2026 10:39AM
The Department cannot grant non-availability waivers. ASTM D8260 Type 1 is acceptable for use on this project.
201 - FORT PECK-NORTHWEST - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:00 PM
New Federal Wage Rates, General Decision Number MT20260080, are now in effect and hereby replaces General Decision Number MT20260079 found in the advertised proposal: WAGE RATES
Questions
-1-
Submitted: Friday 29-MAY-2026 11:51 AM
Company: Riverside Contracting Inc.
Contact: Estimating
Can MDT post the design files, mass diagram, dirt runs, and any additional geotechnical information.
Answer
Submitted: Monday 01-JUN-2026 02:50 PM
The design files for the requested project are posted here: DESIGN FILES
The requested files do not represent the staked project, but are only design files. The Department cannot guarantee the accuracy of the electronic data, particularly as it may be called up by your computer, nor does any data in these files supersede the data in the contract documents.
In addition, the Department will not make any revisions to the electronic files pertaining to the staked project, change ordered work, or changes that are made during construction to fit field conditions.
Linked are PDF Files of the available project alignment and/or structures geotechnical report(s), geotechnical report supplements, and geotechnical laboratory summaries. There is remaining geotechnical information that is voluminous and very difficult to compile in a concise manner. Contractors are welcome to come to MDT Headquarters to inspect rock samples taken for the project that are stored here or to look through the complete set of Geotechnical field investigation notes, laboratory testing, analytical, or other data in our project files. It should be noted that the project may have undergone significant changes during the design process after the original geotechnical report and supplements were issued. Thus, some of the information contained in these documents may be out of date or not applicable with regard to the advertised project. Some of the changes include, but are not limited to: Project splits (for funding, ROW issues, etc.) alignment and grade changes; and changes due to environmental factors (sensitive areas, etc.). The documents can be found at the following link: GEOTECH REPORT
-2-
Submitted: Wednesday 03-JUN-2026 12:38 PM
Company: Riverside Contracting Inc.
Contact: Dennis Devous
Please confirm the Crushed Aggregate bid item. The Additional Surfacing Summary shows 13333 Cy of a leveling Cs. and this isn't added into the Total Bid Crushed Aggregate bid item. Please clarify what you want.
-3-
Submitted: Friday 05-JUN-2026 09:14 AM
Company: Riverside Contracting Inc.
Contact: Estimating
In response to Question 1. The design files appear to be incomplete, lacking a subgrade surface and complete project alignment. There appears to be an inconsistency between the main grading frame and quantities calculated from the cross sections. Can MDT provide a dirt run for the project please?
-4-
Submitted: Sunday 07-JUN-2026 11:30 AM
Company: Prince, Inc.
Contact: Mike Sharp
The NTP date in the proposal is August 24, 2026. Could this project be flexed to April 15th, 2027? The pit permitting process, mix design development and approval, and the fact that the emulsion injection process has limitations (weather, curing, etc..) lends itself to a 2027 start date. And the flexibility of a Flex Date NTP will still allow the successful bidder to work this fall if desired. Thank you.
Answer
Submitted: Tuesday 09-JUN-2026 09:36AM
Contract time will be revised to a flex time proceed date, effective April 19, 2027. Special provision #2, Contract Time is rescinded and replaced with the linked special provision, Contract Time – Flex Time Proceed Date: CONTRACT TIME
-5-
Submitted: Saturday 06-JUN-2026 06:08 PM
Company: Prince, Inc.
Contact: Mike Sharp
1.) There are nearly 100 approaches on the project and no quantities for the obliteration of the existing surfacing on the approaches. How will this obliteration be paid for?
2.) There are also several mailbox widenings that require pulverization that do not appear to have quantities set up in the pulverization summary. Will this be paid under the pulverization item?
3.) It appears that the pulverized pavement quantity is also included in the unclassified excavation quantity. Please provide a detailed breakdown of both quantities to help clarify which is to be paid as unclassified excavation and what is to be paid as pulverization.
4.) The note below the Additional Surfacing summary indicates that there will be 13,333 CY of leveling course material available for leveling. The last two pulverization projects have had either shrink (-4% on Reserve - E.) or zero swell (W. of Jordan - W.). What pay item will be used to address the shortfall if that occurs?
5.) Special Provision 20 reads that Corrective Aggregate (CAC) required for corrective work (leveling and digouts) prior to emulsion injection will be paid by the ton. That pay item and quantity is missing from the proposal. Please add that bid item and quantity to the documents and bid file.
202 - SF 169 CONRAD & 2ND INTX-KAL - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:20 PM
New Federal Wage Rates, General Decision Number MT20260080, are now in effect and hereby replaces General Decision Number MT20260079 found in the advertised proposal: WAGE RATES
Questions
No Questions available for this project.
203 - SLIDE REPAIR-W OF BEARCREEK - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:20 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES
Questions
No Questions available for this project.
204 - I-94 FENCING - TERRY AREA - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:25 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES
Questions
-1-
Submitted: Friday 29-MAY-2026 07:15 AM
Company: Montana Fence
Contact: Jacob Wutke
Referencing Drawing 607-10 - Combination Woven/Barbed is installed with a double panel every 660ft, At changes in directions, and at Corners. Also there is no detailed Drawing for a metal right away break in which case the state has offset a double on one side of the monument pin. Would the state adjust the quantities of Doubles and Singles for both Metal and Wood due to the fact that the the quantities of doubles and singles is currently inaccurate. On All past jobs double panels far exceed the number of Single Panels. Our Quick Estimation taking a look at the Plans is roughly: (F3M-32IN WW) Doubles - 269 Doubles and 56 Singles with 93 Right away Breaks; (F3W-32IN WW) Doubles -20 and Singles -4 with 4 Right away Breaks.
Answer
Submitted: Monday 8-JUN-2026 03:20 PM
Install a double fence panel at all right of way breaks offset 1 foot onto MDT’s right of way. Quantities for the following bid items are hereby amended per the updated summary:
UPDATED PLAN SHEET 3
607100360 FARM FENCE-PANEL/SINGLE FW EACH 4
607100362 FARM FENCE-PANEL/SINGLE FM EACH 101
607100380 FARM FENCE-PANEL/DOUBLE FW EACH 23
607100385 FARM FENCE-PANEL/DOUBLE FM EACH 396
An amendment will be issued; updated bid files will be posted.
-2-
Submitted: Friday 29-MAY-2026 07:21 AM
Company: Montana Fence
Contact: Jacob Wutke
In regards to the Portion on Page 8 Concerning Bald Eagles:
"The specific construction activities required for construction of the new right-of- way fence along I-94, between R.P. 178.1 and R.P. 180.1 along I-94 in Prairie County are excepted from this restriction."
Did the State mean Exempted
Answer
Submitted: Wednesday 03-JUN-2026 08:28AM
While exempted or excepted may be used in this situation, the intent of the special is to allow the construction activities for the fence work to commence without any timing restrictions for the BGEPA between RP 178.1 and 180.1. The contractor will still not be allowed to build man camps or stage material within that area. The timing restrictions in the MBTA special provision for this Project must still be adhered to.
-3-
Submitted: Thursday 04-JUN-2026 08:59 AM
Company: Montana Fence
Contact: Jacob Wutke
In regards to the railroad Flagging and being in the right away- Is the state going to require rail road protective insurance? If So- is this to be figured into our bid or will it be reimbursed in or out of the bid?
Answer
Submitted: Monday 08-JUN-2026 09:15 AM
Railroad Protective and Liability Insurance is required for this project. This can be provided with a separate company policy, or the contractor can choose to go under the RR’s Blanket policy. Per the special provision MDT will reimburse the fee for the cost of the permit.
205 - MALTA-EAST - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:25 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES
Questions
No Questions available for this project.
206 - MILES CITY-WEST - June 25, 2026
Notifications
No Notices available for this project.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Tuesday 09-JUN-2026 01:30 PM
New Federal Wage Rates, General Decision Number MT 20260080 06042026, are now in effect and hereby replaces General Decision Number MT20260080-01302026 found in the advertised proposal: WAGE RATES
Questions
No Questions available for this project.
301 - NEVI PROGRAM - INTERSTATE SYSTEM - July 29, 2026
Notifications
-1-
Submitted: Wednesday 18-MAR-2026 11:00 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on April 7, 2026.
Project Name: NEVI Program- Interstate System
Project No: EV STWD(983)
Control No: 10436000
Project Description:
The Project consists of performing all services necessary to design, construct, operate, and maintain EV charging stations in compliance with the requirements described in the draft Contract included as Attachment 2. The EV charging stations will be located along Montana’s AFCs at locations to be determined by Proposers as described in the draft RFP included as Attachment 1. The work generally includes the following:
• Design and construct a minimum of four network-connected direct current (DC) 150 kilowatt (kW) charging ports, at each EV charging station, capable of simultaneously and continuously charging four EVs, located within approximately a one-mile driving distance of an AFC, and available for use by the public 24 hours per day, seven days per week, and year-round.
• Operate and maintain the EV charging infrastructure for a minimum of five years following EVSE Acceptance pursuant to Section 4.6.4 (EVSE Acceptance) of the Contract in accordance with the O&M Period requirements.
• Provide secure payment methods.
• Collect, process, retain, and share near real-time and static data.
• Provide a minimum of 20 percent of Eligible Project Cost.
The project RFQ and attachments can be found at the following link: RFQ-ATTACHMENTS
-2-
Submitted: Monday 23-MAR-2026 11:36 AM
MDT is hosting an SOQ Webinar at 11:00 am Mountain Time on March 25, 2026, to highlight important components of the RFQ. This informational webinar is open to the public with microphone and video disabled. All questions should be asked through the Q&A Forum in accordance with the RFQ and no questions will be answered during the webinar.
Topic: MDT SOQ Webinar
Time: Mar 25, 2026 11:00 AM Mountain Time (US and Canada)
Join Zoom Meeting
https://mt-gov.zoom.us/j/86089197890?pwd=3zMC8YUcouEzfTThbQAWgacDDVV5lS.1
Meeting ID: 860 8919 7890
Password: 590639
Dial by Telephone
+1 646 558 8656
Meeting ID: 860 8919 7890
Password: 590639
Find your local number: https://mt-gov.zoom.us/u/kbzpCWQBMV
-3-
Submitted: Wednesday 25-MAR-2026 08:35AM
Update to the Personnel Experience Section 3.4 of the RFQ:
The Personnel Experience portion of the SOQ shall not exceed 16, 8.5”x11” pages (two pages maximum for each of the eight resumes). Personnel Experience is a scored element with a scoring total score of 300 points.
-4-
Submitted: Thursday 26-MAR-2026 07:36 AM
NEVI Program SOQ PowerPoint and Webinar: NEVI SOQ
-5-
Submitted: Tuesday 14-APR-2026 11:40 AM
In lieu of the email mdtalternativecontracting@mt.gov provided in Section 2.3: SOQ Submittal of the RFQ, please submit SOQ’s through the file transfer service to Eric Parrish at eparrish@mt.gov and Aubrey Yerger at ayerger@mt.gov. The email (mdtalternativecontracting@mt.gov) appears to be invalid when used with the state file transfer service.
-6-
Submitted: Wednesday 13-MAY-2026 11:13 AM
Shortlisted Firms ( In alphabetical order):
EV Gateway
FTI & SWTCH
Love’s Travel Stops
-7-
Submitted: Thursday 04-JUN-2026 12:23PM
The following attachments to the RFP have had issues opening properly:
- 10436_02_A1_1B_HazMat.pdf
- 10436_02_A1_1C_CatEx.pdf
Working files can be found here: RFP Attachments Working
It should be noted that the files will not open properly in the Microsoft Explorer or Google Chrome Browsers. You will need to right click and force them to be opened with Adobe Acrobat.
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Thursday 26-MAR-2026 11:38AM
The SOQ submittal date posted to the Q&A forum is hereby amended to April 15th at 11:00 a.m. local time to align with the procurement schedule in the RFQ.
-2-
Submitted: Tuesday 07-APR-2026 11:56AM
The Preproposal meeting has been rescheduled for Tuesday, May 26th, 2026, from 12:30 PM to 1:30 PM local time.
-3-
Submitted: Friday 10-APR-2026 08:34AM
The introduction (Page 1, Paragraph 3) of the RFQ is hereby modified as follows:
“Proposers may elect to pursue one, multiple, or all a minimum of three EV charging stations identified in the subsequent Request for Proposals (RFP). Following evaluation of the Statement of Qualifications (SOQs), MDT will identify a shortlist of Proposers that will receive an RFP and may submit a Proposal to MDT. After evaluation of Proposals, Montana Transportation Commission (MTC) will select one NEVI Contractor, and MDT will enter into one three or more EV charging station-specific agreements with the NEVI Contractor. “
-4-
Submitted: Thursday 23-APR-2026 09:16 AM
In support of Q&A clarification #3 the following definition applies:
In accordance with 23 CFR 680.104, EV charging station means the area in the immediate vicinity of a group of chargers and includes the chargers, supporting equipment, parking areas adjacent to the chargers, and lanes for vehicle ingress and egress. A charging station could comprise only part of the property on which it is located.
-5-
Submitted: Thursday 28-MAY-2026 12:35 PM
The following edits are to section 3 Proposal Content Requirements, subsection 3.3 Price Proposal of the RFP:
- Proposer shall enter the NEVI Contractor
ShareContribution (%$) for each EV charging station. The NEVI Contractor Share (%) will be automatically calculated. This percentage must be 20% or higher. - Federal Share of Eligible Costs must not exceed $800,000 for each EV charging station.
- All percentages must be
Share of Eligible Costswhole numbers.
-6-
Submitted: Monday 01-JUN-2026 10:52 AM
The Q&A Forum close date is amended in section 2, subsection 2.2 - Procurement Schedule of the RFP as follows:
| Q&A Forum Closes at 5:00 p.m. local time |
Questions
-1-
Submitted: Thursday 19-MAR-2026 09:18 AM
Company: MN8 Energy
Contact: Brianna Alix
Within the RFQ, it is outlined that there will be an SOQ webinar held on 3/25. Could you please share how we should register for the session?
Answer
Submitted: Monday 23-MAR-2026 11:29 AM
MDT will post the SOQ webinar information as a notification to the Q&A Forum.
-2-
Submitted: Monday 30-MAR-2026 12:59 PM
Company: Voltpost
Contact: Olivia Cosio
Is MDT only interested in DCFC along AFCs? Can these federal funds also go towards Level 2 chargers at the zones outlined in the RFP?
Answer
Submitted: Wednesday 01-APR-2026 08:25 AM
This project will not offer funding for AC level 2 charging ports.
-3-
Submitted: Wednesday 01-APR-2026 08:31 AM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
1. Does the applicant have to apply under joint venture if the EVSE provider is a contractor on the project? Or can we just provide the letter of commitments for them?
2. Can we include cover pages? If so, does that count towards the max page amount limit?
3. Does the percentage of their contributions on a project have to be on the key personnel resume?
4. Do we have to register prior to submission of the SOQ?
5. Does the form have to stay within their individual page limit? For example, if form a is 1 pg, form b is 3pgs, form c is 1 pg, not exceeding 5pgs in total does that suffice?
Answer
Submitted: Thursday 2-APR-2026 03:29PM
1. No, Proposer does not have to propose as a JV. The Proposer can propose as a single entity led by a prime with subcontractors or a JV. If the Proposer intends to form a JV, but has not yet done so, the Proposer can provide a signed letter of intent or teaming agreement stating intent to form a JV if awarded.
2. A cover page may be included for the whole proposal and a cover page to separate each section outlined in the RFQ. These sheets will not count towards the max page limit.
3. No, the percentage contribution/time spent on a particular project doesn’t specifically need to be included on the key personnel resume.
4. Per section 3.4 of the RFQ,"the EVSE Contractor and any other team memeber that will perform construction or installation is required to be a licensed contractor in the state of Montana prior to the execution of the Contract."
5. The Max Pages in scoring table 4.2.1 should be followed for page limits. Each form and section should not exceed the designated page limits.
-4-
Submitted: Monday 13-APR-2026 03:46 PM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
Per the RFQ it states to send the submission to mdtalternativecontracting@mt.gov. However, it states that email is invalid and gives an error. If the submission is sent to the two contacts listed in the RFQ Eric Parrish and Aubrey Yerger, is the submission considered valid and properly submitted?
Answer
Submitted: Tuesday 14-APR-2026 07:17 AM
Yes, the submission received via email to Eric Parrish (eparrish@mt.gov) and Aubrey Yerger (ayerger@mt.gov) is considered valid.
-5-
Submitted: Tuesday 14-APR-2026 07:46 AM
Company: Love's Travel Stops & Country Stores Inc
Contact: Paris Despenza
Are applicants required to acknowledge the clarifications?
Answer
Submitted: Wednesday 15-APR-2026 03:17 PM
Clarifications are considered to be part of the Q&A. Therefore, acknowledgement of the Q&A, as indicated in Section 3.2.1 of the RFQ, is acknowledgement of the clarifications.
302 - GREYCLIFF AREA BRIDGES - September 09, 2026
Notifications
-1-
Submitted: Wednesday 29-APR-2026 09:24 AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on May 27, 2026.
Project Name: GREYCLIFF AREA BRIDGES
Project No: STPB 81014(2)0
Control No: 10661000
Project Description:
The scope of work for this Design-Build Contract includes services required to design and reconstruct six (6) existing bridges along Highway 10 between Greycliff and Big Timber, Montana. The Project involves replacing the aging and deteriorating bridges with new structures and will reconstruct the adjacent roadways as necessary.
The project RFQ and attachments can be found at the following link: RFQ AND ATTACHMENTS
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Monday 11-MAY-2026 02:55 PM
Addition to Section 1., paragraph 2 of the RFQ: When the system prompts the user to enter a delivery email, complete the following steps to submit the SOQ to mdtalternativecontracting@mt.gov: Select the “Find a State Group” tab, type “MDT Alternative Contracting” in the search bar, click the “Search” button, click the “+MDT Alternative Contracting” button after the search has completed, click the “Send” button.
Questions
-1-
Submitted: Friday 08-MAY-2026 02:39 PM
Company: Morrison-Maierle
Contact: Luke Carlson
Can the table that defines which Phase 1 Documents are Bridging Documents and which are provided for informational purposes only be provided now, so firms can assess the required design effort, the relative value of the stipend, and the ability to meet the project completion date?
Answer
Submitted: Tuesday 12-MAY-2026 03:41PM
The table that defines which Phase 1 Documents are Bridging Documents is being developed and not available. The following is a preliminary list of Bridging Documents that will be provided with the RFP: Preliminary Geotechnical Field Investigation Report, Categorical Exclusion, Scope of Work Report, SHARES Reports and Hydraulic Models, Control Survey, Cadastral Survey, Engineering Survey, and Structure Type, Size and Location Report. The contractual Bridging Documents will be identified and provided with the RFP and will supersede the preliminary list provided within this response.
-2-
Submitted: Friday 08-MAY-2026 02:36 PM
Company: Morrison-Maierle
Contact: Luke Carlson
Will MDT entertain Alternative Technical Concepts to allow teams to best meet MDT design requirements and project goals?
Answer
Submitted: Tuesday 12-MAY-2026 03:55PM
Alternative Technical Concepts are not allowed on this project. Proposed deviations from the Contract requirements must be submitted as questions through the Q&A Forum.
-3-
Submitted: Friday 08-MAY-2026 03:41 PM
Company: Frontier West LLC
Contact: Kris Anderson
Would MDT consider extending the duration between the release of the RFP and the technical proposal due date timeline if the Phase 1 work does not include roadway or bridge design or plans?
Answer
Submitted: Tuesday 12-MAY-2026 04:02PM
The Phase 1 Documents will include a preliminary road plan and profile sheet for each site. The associated electronic CAD files will be provided with the Phase 1 Documents attached to the RFP. The draft RFP requires the Firm to only submit a road plan and profile sheet for each site with the Technical Proposal. The Tentative Schedule of Events within the RFQ is unchanged.
-4-
Submitted: Friday 08-MAY-2026 03:41 PM
Company: Frontier West LLC
Contact: Kris Anderson
The preliminary drawings provided with the RFQ do not appear to provide any bridge or roadway design information. Will MDT increase the stipend if the Phase 1 work does not include roadway and bridge plans and design?
Answer
Submitted: Tuesday 12-MAY-2026 04:05PM
The Phase 1 Documents will include a preliminary road plan and profile sheet for each site and the associated electronic CAD files. The stipend will not be increased.
-5-
Submitted: Friday 15-MAY-2026 12:01 PM
Company: Forsgren Associates
Contact: Nathan Haddick
Section VI. A. 1. g. of the RFQ states: "The prime contractor, design professional, and key personnel (including the individual’s employer) are exclusive to the Firm and cannot team with another Firm to submit more than one SOQ per Project." Does this restriction preclude a subconsultant or subcontractor from being included on multiple teams submitting SOQ's for this project if they are not listed as Key Personnel?
Answer
Submitted: Wednesday 20-MAY-2026 08:25 AM
Individuals assigned as Key Personnel and their employer are exclusive to the Firm and cannot be associated with multiple Firms. All other companies, besides those assigned with Key Personnel, may team with multiple Firms.
303 - MILL CREEK HIGHWAY - September 22, 2026
Notifications
-1-
Submitted: Wednesday 15-APR-2026 11:36AM
The Montana Department of Transportation (MDT) is soliciting design and construction services for the Design-Build project identified below. Contractor and consultant teams (Firms) are encouraged to submit a Statement of Qualifications (SOQ) response electronically by 11:00 a.m., local time on May 13, 2026.
Project Name: MILL CREEK HIGHWAY
Project No: SSS 569-1(11)6
Control No: 10473000
Project Description:
The scope of work for this Design-Build contract includes reconstruction of approximately five miles of Secondary Highway 569 (S-569), also known as Mill Creek Highway, from reference post (RP) 6.11 to RP 11.0. The project is funded by a RAISE grant awarded to Anaconda-Deer Lodge County (ADLC). The project is intended to address existing deficiencies and improve safety. The roadway will be reconstructed to include 12-foot driving lanes and 1-foot shoulders. Additionally, the project will improve roadway geometrics and reconstruct the existing pavement with new bituminous surfacing. The project will also include new centerline rumble strips, pavement markings, signage, guardrail, improved clear zones and side slopes, and improved hydraulics, culvert and storm water infrastructure.
The project RFQ and attachments can be found at the following link: RFQ AND ATTACHMENTS
-2-
Submitted: Monday 01-JUN-2026 07:06 AM
Short-listed Firms (in alphabetical order)
- Montana Materials & Construction and KLJ Engineering
- Riverside Contracting and Morrison-Maierle
- Schellinger Construction and DJ&A
Amendments
No Amendments available for this project.
Clarifications
-1-
Submitted: Thursday 07-MAY-2026 01:26 PM
Modification to Section I., paragraph 2 of the RFQ: When submitting SOQ through the File Transfer Service, submit the SOQ to the following email addresses: ayerger@mt.gov and bgraff@mt.gov. Do not submit SOQ to mdtalternativecontracting@mt.gov
Questions
-1-
Submitted: Monday 08-JUN-2026 11:00 AM
Company: Morrison-Maierle
Contact: Bryan Vanderloos
Can MDT confirm the guardrail type for the project? The RFP calls out Box-Beam, but the Phase 1 plans show MGS guardrail.