May 27, 2025

This week, crews will continue working on the drainage bridge just west of Ingomar (Bridge ID 5496), at mile marker 229 on U.S. Highway 12. They will install additional box culvert sections and backfill around them at this site. Backfilling consists of putting soil around the new sections to support them and help them stay in place.

A shoofly detour remains in place to guide traffic safely around the work zone. The new box culvert at this location is partially installed, and work this week focuses on completing the installation.

In addition to ongoing work at Bridge 5496, crews will continue off-road preparation at the drainage ditch 2 miles northwest of West Blacktail Road (Bridge ID 5497), at mile marker 236.

These are the only active sites in the project area at this time.

Please reduce your speed, follow signage, and remain alert when traveling through the area. Your patience helps ensure a safe work zone for everyone.

May 19, 2025

This week, crews will remove the existing bridge structure at Bridge ID 5496, located just west of Ingomar at mile marker 229. A shoofly detour is now in place to keep traffic moving safely around the work zone.

A new box culvert at this location is partially in place, which is part of the Montana Department of Transportation's (MDT) plan for bridge construction to proceed in stages, with the current detour in place over the new structure. This method avoids fully removing the roadway at once, helping minimize disruption for drivers. Temporary detours will be used as needed, rather than a permanent closure.

This is the only active work site in the project area at this time.

Please slow down, follow signage, and use the temporary detours.

To accommodate holiday traffic over Memorial Day weekend, no work will occur from Friday afternoon, May 23, through Monday, May 26. Normal work hours will resume Tuesday, May 27.

May 12, 2025

This week, on the Timber Bridges – Forsyth Area project, box culvert installation work continues on the drainage ditch just west of Ingomar (Bridge ID 5496) at mile marker 229. Crews are "back-filling" around the new concrete culvert, meaning they are putting soil back around the structure to support it and help it stay in place.

Crews are also continuing site preparation for future culvert installation at the drainage ditch 2 miles northwest of West Blacktail Road (Bridge ID 5497), at mile marker 236.

Please slow down, follow signage, and use the temporary detours.

Cutoff Wall setting RCB RCB in place

May 5, 2025

Work is progressing on the Timber Bridges – Forsyth Area project.

This week, now that crews have built a temporary detour, box culvert installation has begun on the drainage ditch just west of Ingomar (Bridge ID 5496) at mile marker 229.

Crews are also continuing site preparation for future culvert installation at the drainage ditch 2 miles northwest of West Blacktail Road (Bridge ID 5497) at mile marker 236 and at the stockpass 90 yards east of Swanson Lane (Bridge ID 5508) at mile marker 257.

Please continue to drive cautiously in the area, follow posted speed limits, and watch for construction crews and equipment. We appreciate your patience as work continues!

April 28, 2025

Work is progressing on the Timber Bridges - Forsyth Area project. This week, now that crews have built a temporary detour, work will begin on the removal of the old bridge structure on the drainage ditch just west of Ingomar (Bridge ID 5496) at mile marker 229.

Crews will also be prepping the road for construction at the drainage ditch 2 miles northwest of West Blacktail Road (Bridge ID 5497) at mile marker 236 and at the stockpass 90 yards east of Swanson Lane (Bridge ID 5508) at mile marker 257. This includes pulverizing and regrading the areas connecting to the bridges so they are ready when full work begins.

Please continue to drive cautiously in the area, follow posted speed limits, and watch for construction signage and equipment. We appreciate your patience as work continues!

April 21, 2025

Construction on the Timber Bridges - Forsyth Area project will start on April 21. Crews will begin work on the drainage ditch just west of Ingomar (Bridge ID 5496) at mile marker 229. Signage will be posted throughout the area to help guide drivers safely through the work zone.

Travelers can expect:

  • Temporary detours (shoofly routes), which will maintain traffic flow at select locations; these routes will be clearly marked
  • Alternating single-lane closures with flaggers or traffic signals
  • Short-term width restrictions (16 feet standard; occasional 12-foot restrictions for up to 5 days with advance notice)
  • Continued access to emergency vehicles, school buses, and agricultural equipment

Please watch for signs, follow posted speeds, and allow extra time when traveling through the area.

National Work Zone Awareness Week
April 21-25, 2025 | nwzaw.org

Respect the zone, so we all get home.

In 2023, 282 work zone crashes occurred in Montana. This construction season, MDT urges Montana drivers and visitors to use extra caution while traveling through work zones by paying attention and following posted signage.

Our families thank you.