Anticipated Schedule

Project award: April 2021
Design: Spring/Summer 2021
Public Open House: July 20 and 21, 2021
Start construction of rest area: Summer/Fall 2021
Construction on US 287: Summer 2022
Opening of Headwaters Rest Area: Late Summer 2022
Closing of Bozeman Rest Area: Late Summer 2022