May 23, 2025

The Montana Department of Transportation (MDT) and CK May Excavating plan to continue removing a large amount of rock on Interstate 90 (I-90) near Bozeman Pass the week of May 25. A second 30-minute closure of I-90 and the West Bozeman Hill Road / U.S. Highway 10 frontage road is necessary to complete controlled rock excavation operations. The closure is expected to take place on Thursday, May 29 between 9:30 a.m. and 3:30 p.m. MDT is unable to provide the specific time the 30-minute closure will occur due to nearby train activity on the BNSF railroad. Plan for delays of up to 1 hour if you have time-sensitive travel during the closure window. If additional 30-minute closures are necessary to remove the rock, advance notice will be provided to the public. Only one closure lasting 30 minutes is expected per day.

Once crews have completed rock removal and roadways are safe for motorists to travel on, roads will reopen in both directions under the existing single-lane closures with reduced speeds. Visit 511mt.net for the most up-to-date information on width restrictions and other traffic control.

What to expect during construction:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Width restrictions

Visit 511mt.net for the most up to date information.

May 20, 2025

The Montana Department of Transportation (MDT) and CK May Excavating have completed the first controlled rock excavation operation near Bozeman Pass. Interstate 90 (I-90) and the West Bozeman Hill Road / U.S. Highway 10 frontage road have now been reopened in both directions under the existing single-lane closures with reduced speeds. Visit 511mt.net for the most up-to-date information on width restrictions and other traffic control.

MDT reminds motorists to obey posted speed limits and traffic laws on I-90 and the West Bozeman Hill Road / U.S. Highway 10 frontage road. For the safety of workers and travelers, there will be increased law enforcement presence near the project area.

What to expect during construction:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Width restrictions

Visit 511mt.net for the most up to date information.

May 13, 2025

The Montana Department of Transportation (MDT) and CK May Excavating are planning to remove a large amount of rock on Interstate 90 (I-90) near Bozeman Pass the week of May 19. A 30-minute closure of I-90 and the West Bozeman Hill Road / U.S. Highway 10 frontage road is necessary to complete controlled rock excavation operations. The closure is expected to take place on Tuesday, May 20 between 9:30 a.m. and 3:30 p.m. MDT is unable to provide the specific time the 30-minute closure will occur due to nearby train activity on the BNSF railroad. Plan for delays of up to 1 hour if you have time-sensitive travel during the closure window. If additional 30-minute closures are necessary to remove the rock, advance notice will be provided to the public. Only one closure lasting 30 minutes is expected per day.

Once crews have completed rock removal and roadways are safe for motorists to travel on, roads will reopen in both directions under the existing single-lane closures with reduced speeds. Visit 511mt.net for the most up-to-date information on width restrictions and other traffic control.

What to expect during construction:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Width restrictions

Visit 511mt.net for the most up to date information.

May 2, 2025

The Montana Department of Transportation (MDT) and CK May Excavating are continuing construction this week between the Jackson Creek Road Interchange (Exit 319) and the Interstate 90 (I-90) Business Loop Interchange (Exit 330) west of Livingston. Work includes milling and paving the eastbound shoulder of I-90 beginning near the Jackson Creek Road Interchange (Exit 319). Rock excavation work is also taking place, and crews expect to soon begin milling the westbound shoulder of I-90 near the I-90 Business Loop (Exit 330). All work is weather dependent.

What to expect during construction:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Width restrictions

Visit 511mt.net for the most up to date information.

April 21, 2025

The Montana Department of Transportation (MDT) and CK May Excavating are continuing construction this week between the Jackson Creek Road Interchange (Exit 319) and the Interstate 90 (I-90) Business Loop Interchange (Exit 330) west of Livingston. Work includes milling and paving the eastbound shoulder of I-90 beginning near the Jackson Creek Road Interchange (Exit 319). All work is weather dependent. Work on ramps has been postponed due to heavy snow and winds in the project area last week. The work will be rescheduled later in the project.

What to expect during construction:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Width restrictions

Visit 511mt.net for the most up to date information.

April 11, 2025

The Montana Department of Transportation (MDT) and CK May Excavating are rehabilitating approximately 11 miles of Interstate 90 (I-90) on Bozeman Pass in Gallatin and Park counties starting the week of April 14.

The project is located between the Jackson Creek Road Interchange (Exit 319) and the I-90 Business Loop Interchange (Exit 330) west of Livingston.

What to expect during construction:

Temporary ramp closures are anticipated at Exit 319 (Jackson Creek Road) and Exit 324 (Flynn Creek Road) the week of April 14, weather and other factors permitting. Motorists will need to use an alternate route during ramp closures.

When construction begins, motorists can expect:

  • Flaggers directing traffic at times
  • I-90 traffic reduced to one lane in each direction
  • Reduced speed limits
  • Exit 319 (Jackson Creek Road)
    • Eastbound on-ramp and westbound off-ramp will be closed April 18.
  • Exit 324 (Flynn Creek Road)
    • Eastbound on- and off-ramps will be closed April 14 and 15.
    • Westbound on- and off-ramps will be closed April 15 through 17.
  • Width restrictions throughout the project area.

Visit 511mt.net for the most up to date information.