Manhattan ADA

Manhattan ADA logo

Project Updates

August 14, 2020

  • Crews will be hard at work in Manhattan finishing up concrete work by the end of next week. Crews will return to install signs and pavement markings in approximately 30 days. That work will complete the project.

Previous Updates

August 7, 2020

  • Construction will continue on Dry Creek Road and is forecasted to be completed by mid week. Concrete work on Broadway is planned for completion next week as well. This will conclude all concrete work on the project by the end of next week. Cleanup will begin the week following.

July 31, 2020

  • This week construction crews concluded their work on Main Street. Sidewalks along Main Street are now fully open for use. Next week, crews will move to Dry Creek Road, with the majority of construction there planned to be completed by the end of next week.

July 24, 2020

  • Crews have finished their first week working in Manhattan. Next week, they will be pouring concrete and backfilling on Main Street. They will also begin demolition work on Dry Creek, working from South to North.