Quartz Flats Rest Area

Project Overview
The Montana Department of Transportation is improving the Quartz Flats Rest Areas on Interstate 90 between Superior and Alberton. The rest area serves travelers year round, and is the gateway to the U.S. Forest Service Quartz Flat campground during the summer.
The planned improvements include:
- Reconstructing rest area buildings
- Increasing wastewater system capacity
- Improving water treatment systems
- Reconstructing parking lot to increase capacity
The Quartz Flats Rest Area was originally built in 1967 and rehabilitated in 1989. The facilities are showing signs of wear and tear and are designed for lower traffic volumes. The improvements will provide new facilities, reduce maintenance costs, and prevent wear and tear.

Click to view a larger image.
Anticipated Project Schedule
Final Plan Report completed: | Summer 2020 |
Construction plans developed | Fall/Winter 2020 |
Construction plans finalized | Spring 2021 |
Construction begins | Summer 2021 |
Construction completed | Summer 2022 |
Stay Involved
Public involvement is important to MDT and the success of the project. The community will be notified about public involvement opportunities through the project website, local media, mailings, social media and other communication channels throughout the project development process. Questions and comments can be directed to Brandon Coates via email or by phone at 406-465-3350.
UPN 6875001