May 18, 2026

This week:

  • Work is underway on First Street (U.S. Highway 2), beginning at Third Avenue West and progressing eastbound in the outside lane.
  • Crews are removing and replacing damaged concrete panels and completing other repairs as part of the first phase of work.
  • Surface grinding will begin in a second phase once most panel repairs are complete.
  • Work will occur in four- to five-block segments and will move from the outer lanes toward the center of the roadway in stages.

Traffic Control

  • Traffic has been reduced to one lane in each direction and is being guided by traffic control devices in active work areas.
  • Minimal delays are anticipated, but travelers should plan for extra time. Speeds will be reduced to 25 to 35 mph, or the posted speed, whichever is lower.
  • Access to businesses will be maintained and clearly marked with traffic control devices.
  • Wide loads are not restricted at this time but may be delayed depending on current operations.

Construction Schedule

  • Crews will typically work during daylight hours, Monday through Friday, weather and other factors permitting.
  • To accommodate holiday traffic, there will be no construction starting at noon Friday, May 22, through Monday, May 25. Work will resume Tuesday, May 26.