- Draft Environmental Documentation - UPDATED October 2019
- Biological Assessment - September 13, 2018
- Draft Categorical Exclusion Form - August 27, 2019
- Draft Environmental Engineering Analysis - October 15, 2019
- Draft Programmatic Section 4(f) Evaluation - August 30, 2019
- HDR Response to Missoula County Commission Comments - September 9, 2019
- Maclay Bridge Preservation Alternatives-January 2019
- FHWA-MDT-Missoula County-HDR Environment Review Meeting - October 27, 2017
- FHWA-MDT-Missoula County-HDR Environmental Review Meeting - January 14, 2016
- Maclay Bridge Options Evaluation - February 24, 2022
- Missoula Board of County Commissioners Presentation-March 12, 2019
- 2019-09-09 Responses to Missoula County Commission Comments
- 6296000 Maclay Bridge Preservation Options Jan 2019
- 6296000ENBAZ01 2018 09 13 Biological Assessment
- Draft Environmental Engineering Analyses 2019-10-15
- Draft Categorical Exclusion Form 2019-10-15
- Draft Programmatic Section 4f Evaluation 2019-08-30
- Presentation
- Missoula County Commissioners Presentation - August 31, 2016
- Missoula County Community and Planning Services (CAPS) Presentation - January 17, 2017
- Project Documents
- Project Meeting Minutes
- Public Meeting #2 - August 16, 2016
- Public Meeting #1 - September 22, 2015
- Reports
- Bridge Type Size and Location Report - October 2016
- HRA Cultural Resources Assessment - February 2016
- Noise Analysis Report - November 2016
- Preliminary Geotechnical and Materials Report - July 2016
- Preliminary Hydraulics Report - July 2016
- Preliminary Roadway and Traffic Report - November 2016
- UPDATED Biological Resource Report - January 2017
- Resource Agency Meeting - August 19, 2016
- Technical Design Committee (TDC) Meeting #1-May 13, 2016
- TDC Meeting #2-June 14, 2016
- TDC Meeting #3-July 19, 2016
- TDC Meeting #4-August 31, 2016
- TDC Meeting #5-January 25, 2017